What are the deshuttering time for
Salb
Beam
Column
RCC Wall
Footing
Staircase




Answers were Sorted based on User's Feedback



What are the deshuttering time for Salb Beam Column RCC Wall Footing Staircase ..

Answer / tanmay

For columns, walls, vertical form works : 16-24 hrs
Soffit formwork to slabs : 3 days (props to be refixed after removal)
Soffit to beams props : 7 days props to refix after removal.
Spanning up to 4.50m : 7 days
Spanning over 4.50m : 14 days
Staircase : 5 days
Footing : 16-24 hours

Is This Answer Correct ?    117 Yes 8 No

What are the deshuttering time for Salb Beam Column RCC Wall Footing Staircase ..

Answer / hany

Beam sides- 24 hrs.
Beam(spanning upto 3mtrs) bottom- 10 days
Beam(spanning more than 3mtrs) bottom- 21 days
slab (spanning upto 3mtrs)- 7 days
Slab (spanning more than 3mtr)- 14 days
rcc wall- 24 hrs
Footing- 24 hrs
Staircase soffit- 7 days

Is This Answer Correct ?    38 Yes 10 No

What are the deshuttering time for Salb Beam Column RCC Wall Footing Staircase ..

Answer / b m sarwe

Beams 21 days
beams side 1 day after casting
slab 7-14 days
columns 1 day after casting
wall 1 day after casting
footing casting next day
Deshuttering works

Is This Answer Correct ?    6 Yes 2 No




What are the deshuttering time for Salb Beam Column RCC Wall Footing Staircase ..

Answer / swadesh

aprox 7 Days for Slab (If RCC used from Batching Plant)

Is This Answer Correct ?    13 Yes 10 No

What are the deshuttering time for Salb Beam Column RCC Wall Footing Staircase ..

Answer / farhat abbas naqvi

For deshuttering any concrete structure after pour to take in note the climate and design mix. For columns and beams sizes plays the major role. Usage of flyash also plays role in settling time.

Is This Answer Correct ?    4 Yes 2 No

What are the deshuttering time for Salb Beam Column RCC Wall Footing Staircase ..

Answer / h r mishra

Slab 7 days
Beam 10 days
wall, footings 24 hours

Is This Answer Correct ?    4 Yes 5 No

What are the deshuttering time for Salb Beam Column RCC Wall Footing Staircase ..

Answer / simon nagaiya

Formwork Removal Time
-------------------------------
Sides of Walls, Columns and Vertical faces of beam - 24 hours to 48 hours (as per engineer’s decision)

Slabs (props left under) - 3 days

Beam soffits (props left under) - 7 days

*Removal of Props of Slabs:*

i)Slabs spanning up to 4.5m - 14 days

ii)Slabs spanning over 4.5m - 14 days

*Removal of props for beams and arches*

i)Span up to 6m - 14 days

ii)Span over 6m - 21 days

Is This Answer Correct ?    2 Yes 4 No

What are the deshuttering time for Salb Beam Column RCC Wall Footing Staircase ..

Answer / krishan

slab-7days
columan-24hours
beam bottom-3days
beam side-24hours
rcc wall-48hours
footing-12hours
staircase-7days

Is This Answer Correct ?    6 Yes 9 No

What are the deshuttering time for Salb Beam Column RCC Wall Footing Staircase ..

Answer / md.khorshed alam

slab-14days
columan-24hours
beam bottom-7days
beam side-24hours
rcc wall-48hours
footing-12hours
staircase-7days

Is This Answer Correct ?    1 Yes 4 No

What are the deshuttering time for Salb Beam Column RCC Wall Footing Staircase ..

Answer / rajesh.d.v.s.p.

for columns=1day
for beams and slabs=14 days
rcc walls= 1day
fotting 1day
stair case=7 days

Is This Answer Correct ?    2 Yes 6 No

Post New Answer



More Civil Engineering Interview Questions

As per IS 456 2000 Clause 16, table 11, page no. 30, it is written that acceptance strength of concrete is fck+4 for grade above M20. what is the meaning of " Mean of the group of 4 Non- overlapping consecutive test results"

0 Answers   Ashiana Housing,


what is th consuption of cement , sand in plastering for 15mm thick cm1:4,1:3

1 Answers  


how to placeing reinforcement in slab?

2 Answers  


what ratio of cement and sand we used for making cover

4 Answers  


How much cement,sand,bricks and water needed for 1square metre brick work?

0 Answers  






Where hinge support is used in residential building?

2 Answers  


what is the main difference b/w compaction and consolidation

2 Answers   KCP,


If 600mm*200mm*150** size bricks comes 55 piece in one cubic meter then how many 230mm*115mm*75 bricks in one cubic meter

1 Answers   Bismi Group,


why 1.25 factor is to be multiplied to cylindrical strength of concrete while getting the equvalent cubical strength of concrete?

10 Answers  


say the propotions of different concrete mix desidn(M20 M15 M25 M25 M30)

4 Answers   Hayat,


a sewer which receives the discharge of no. of house sewer is called house sewer lateral sewer intrcepting sewer sub-main sewer

0 Answers  


what is stressing

1 Answers   Simplex,






Categories
  • Civil Engineering Interview Questions Civil Engineering (4636)
  • Mechanical Engineering Interview Questions Mechanical Engineering (3700)
  • Electrical Engineering Interview Questions Electrical Engineering (15765)
  • Electronics Communications Interview Questions Electronics Communications (2636)
  • Chemical Engineering Interview Questions Chemical Engineering (762)
  • Aeronautical Engineering Interview Questions Aeronautical Engineering (79)
  • Bio Engineering Interview Questions Bio Engineering (30)
  • Metallurgy Interview Questions Metallurgy (95)
  • Industrial Engineering Interview Questions Industrial Engineering (199)
  • Instrumentation Interview Questions Instrumentation (2879)
  • Automobile Engineering Interview Questions Automobile Engineering (171)
  • Mechatronics Engineering Interview Questions Mechatronics Engineering (41)
  • Marine Engineering Interview Questions Marine Engineering (62)
  • Power Plant Engineering Interview Questions Power Plant Engineering (169)
  • Engineering AllOther Interview Questions Engineering AllOther (1334)