What are the deshuttering time for Salb Beam Column RCC Wall Footing Staircase ..

Answer / tanmay

For columns, walls, vertical form works : 16-24 hrs
Soffit formwork to slabs : 3 days (props to be refixed after removal)
Soffit to beams props : 7 days props to refix after removal.
Spanning up to 4.50m : 7 days
Spanning over 4.50m : 14 days
Staircase : 5 days
Footing : 16-24 hours

Is This Answer Correct ?    119 Yes 8 No

What are the deshuttering time for Salb Beam Column RCC Wall Footing Staircase ..

Answer / hany

Beam sides- 24 hrs.
Beam(spanning upto 3mtrs) bottom- 10 days
Beam(spanning more than 3mtrs) bottom- 21 days
slab (spanning upto 3mtrs)- 7 days
Slab (spanning more than 3mtr)- 14 days
rcc wall- 24 hrs
Footing- 24 hrs
Staircase soffit- 7 days

Is This Answer Correct ?    39 Yes 10 No

What are the deshuttering time for Salb Beam Column RCC Wall Footing Staircase ..

Answer / b m sarwe

Beams 21 days
beams side 1 day after casting
slab 7-14 days
columns 1 day after casting
wall 1 day after casting
footing casting next day
Deshuttering works

Is This Answer Correct ?    7 Yes 2 No




What are the deshuttering time for Salb Beam Column RCC Wall Footing Staircase ..

Answer / swadesh

aprox 7 Days for Slab (If RCC used from Batching Plant)

Is This Answer Correct ?    13 Yes 10 No

What are the deshuttering time for Salb Beam Column RCC Wall Footing Staircase ..

Answer / farhat abbas naqvi

For deshuttering any concrete structure after pour to take in note the climate and design mix. For columns and beams sizes plays the major role. Usage of flyash also plays role in settling time.

Is This Answer Correct ?    4 Yes 2 No

What are the deshuttering time for Salb Beam Column RCC Wall Footing Staircase ..

Answer / h r mishra

Slab 7 days
Beam 10 days
wall, footings 24 hours

Is This Answer Correct ?    4 Yes 5 No

What are the deshuttering time for Salb Beam Column RCC Wall Footing Staircase ..

Answer / simon nagaiya

Formwork Removal Time
-------------------------------
Sides of Walls, Columns and Vertical faces of beam - 24 hours to 48 hours (as per engineer’s decision)

Slabs (props left under) - 3 days

Beam soffits (props left under) - 7 days

*Removal of Props of Slabs:*

i)Slabs spanning up to 4.5m - 14 days

ii)Slabs spanning over 4.5m - 14 days

*Removal of props for beams and arches*

i)Span up to 6m - 14 days

ii)Span over 6m - 21 days

Is This Answer Correct ?    2 Yes 4 No

What are the deshuttering time for Salb Beam Column RCC Wall Footing Staircase ..

Answer / krishan

slab-7days
columan-24hours
beam bottom-3days
beam side-24hours
rcc wall-48hours
footing-12hours
staircase-7days

Is This Answer Correct ?    6 Yes 9 No

What are the deshuttering time for Salb Beam Column RCC Wall Footing Staircase ..

Answer / md.khorshed alam

slab-14days
columan-24hours
beam bottom-7days
beam side-24hours
rcc wall-48hours
footing-12hours
staircase-7days

Is This Answer Correct ?    1 Yes 4 No

What are the deshuttering time for Salb Beam Column RCC Wall Footing Staircase ..

Answer / rajesh.d.v.s.p.

for columns=1day
for beams and slabs=14 days
rcc walls= 1day
fotting 1day
stair case=7 days

Is This Answer Correct ?    2 Yes 6 No

Post New Answer



More Civil Engineering Interview Questions

Engineering method, why need is column kiker??? what is necessity??

0 Answers   BNF Group,


What is the Content in RCC M 35 Grade e.g water content,sand,metal ,cement etc.

4 Answers  


what is workability,define it?

2 Answers  


what is the average steel consumption in multy storey building as a residential and commercial?

6 Answers  


what is differences between ferrock and concrete ?

0 Answers  






what is the least count of staff ?

12 Answers   UltraTech, CCCL,


Plaster area is 1000 sqft thickness is 12 mm so what will be the quantity of cement and sand

1 Answers  


What is the maximum allowable wastage in pouring of Ready Mix Concrete received at location with transit mixtures. Work scope includes both Direct Pouring & manual pouring.

1 Answers   AKM Construction Management,


which method is used in semi-rigid connection design??

0 Answers   L&T,


How to find CN by using arcgis 9.3?

0 Answers  


What are the tests on concrete?

1 Answers  


how many days we should curing for plastering,brickwork,concrete?

10 Answers   CCCL, Wipro, Consolidated Construction Consortium Limited, Alfaraa, Al Faraa,






Categories
  • Civil Engineering Interview Questions Civil Engineering (4645)
  • Mechanical Engineering Interview Questions Mechanical Engineering (3704)
  • Electrical Engineering Interview Questions Electrical Engineering (15785)
  • Electronics Communications Interview Questions Electronics Communications (2638)
  • Chemical Engineering Interview Questions Chemical Engineering (762)
  • Aeronautical Engineering Interview Questions Aeronautical Engineering (79)
  • Bio Engineering Interview Questions Bio Engineering (30)
  • Metallurgy Interview Questions Metallurgy (95)
  • Industrial Engineering Interview Questions Industrial Engineering (199)
  • Instrumentation Interview Questions Instrumentation (2882)
  • Automobile Engineering Interview Questions Automobile Engineering (171)
  • Mechatronics Engineering Interview Questions Mechatronics Engineering (41)
  • Marine Engineering Interview Questions Marine Engineering (62)
  • Power Plant Engineering Interview Questions Power Plant Engineering (170)
  • Engineering AllOther Interview Questions Engineering AllOther (1336)