What are the deshuttering time for
Salb
Beam
Column
RCC Wall
Footing
Staircase

Answers were Sorted based on User's Feedback



What are the deshuttering time for Salb Beam Column RCC Wall Footing Staircase ..

Answer / tanmay

For columns, walls, vertical form works : 16-24 hrs
Soffit formwork to slabs : 3 days (props to be refixed after removal)
Soffit to beams props : 7 days props to refix after removal.
Spanning up to 4.50m : 7 days
Spanning over 4.50m : 14 days
Staircase : 5 days
Footing : 16-24 hours

Is This Answer Correct ?    126 Yes 8 No

What are the deshuttering time for Salb Beam Column RCC Wall Footing Staircase ..

Answer / hany

Beam sides- 24 hrs.
Beam(spanning upto 3mtrs) bottom- 10 days
Beam(spanning more than 3mtrs) bottom- 21 days
slab (spanning upto 3mtrs)- 7 days
Slab (spanning more than 3mtr)- 14 days
rcc wall- 24 hrs
Footing- 24 hrs
Staircase soffit- 7 days

Is This Answer Correct ?    40 Yes 10 No

What are the deshuttering time for Salb Beam Column RCC Wall Footing Staircase ..

Answer / b m sarwe

Beams 21 days
beams side 1 day after casting
slab 7-14 days
columns 1 day after casting
wall 1 day after casting
footing casting next day
Deshuttering works

Is This Answer Correct ?    8 Yes 2 No

What are the deshuttering time for Salb Beam Column RCC Wall Footing Staircase ..

Answer / swadesh

aprox 7 Days for Slab (If RCC used from Batching Plant)

Is This Answer Correct ?    13 Yes 10 No

What are the deshuttering time for Salb Beam Column RCC Wall Footing Staircase ..

Answer / farhat abbas naqvi

For deshuttering any concrete structure after pour to take in note the climate and design mix. For columns and beams sizes plays the major role. Usage of flyash also plays role in settling time.

Is This Answer Correct ?    4 Yes 2 No

What are the deshuttering time for Salb Beam Column RCC Wall Footing Staircase ..

Answer / h r mishra

Slab 7 days
Beam 10 days
wall, footings 24 hours

Is This Answer Correct ?    5 Yes 5 No

What are the deshuttering time for Salb Beam Column RCC Wall Footing Staircase ..

Answer / kirishnasekar m

all sides - next day itself (24 hours)

slab < 4.5 m-7 days

slab > 4.5 m-14 days

beam & arches < 6.0 m-14 days

beam & arches > 6.0 m-21 days

staircase waist-7days, after removal of shutter, props to be fixed for 3 days

Is This Answer Correct ?    0 Yes 0 No

What are the deshuttering time for Salb Beam Column RCC Wall Footing Staircase ..

Answer / simon nagaiya

Formwork Removal Time
-------------------------------
Sides of Walls, Columns and Vertical faces of beam - 24 hours to 48 hours (as per engineer’s decision)

Slabs (props left under) - 3 days

Beam soffits (props left under) - 7 days

*Removal of Props of Slabs:*

i)Slabs spanning up to 4.5m - 14 days

ii)Slabs spanning over 4.5m - 14 days

*Removal of props for beams and arches*

i)Span up to 6m - 14 days

ii)Span over 6m - 21 days

Is This Answer Correct ?    3 Yes 4 No

What are the deshuttering time for Salb Beam Column RCC Wall Footing Staircase ..

Answer / krishan

slab-7days
columan-24hours
beam bottom-3days
beam side-24hours
rcc wall-48hours
footing-12hours
staircase-7days

Is This Answer Correct ?    6 Yes 9 No

What are the deshuttering time for Salb Beam Column RCC Wall Footing Staircase ..

Answer / md.khorshed alam

slab-14days
columan-24hours
beam bottom-7days
beam side-24hours
rcc wall-48hours
footing-12hours
staircase-7days

Is This Answer Correct ?    1 Yes 4 No

Post New Answer

More Civil Engineering Interview Questions

what are the criteria for choosing the span for the bridge (highway bridge)

4 Answers  


calculation of cement bags in 1:2:4 concrete mix

26 Answers  


Explain major differences between routing maintenance and major maintenance.

0 Answers  


where we use one way slab and two way slab?

7 Answers   SRM,


Gave a cantilever beam with 3 legs.Told to draw the bending moment diagrams, axial force diagrams and shear force diagrams.From BMD he asked to show how the reinforcement will be provided on the tension side.

0 Answers   L&T,






Why curing is necessary for concrete

6 Answers  


1M2=how much M3?

7 Answers  


how much steel required for 1 sq.m area?

12 Answers   L&T,


1) What is meant by C-soil in geotechnical Engineering? 2) What is Eve board? 3) What will happen when heat is applied to cement? 4) what do you understand by the lateral dimention ?

0 Answers   Public Service Commission,


what"s the merits and demerits of hollow blocks comapre than to bricks?

1 Answers   Punj Lloyd Ltd,


what is quick sand

4 Answers  


what is dead wall?

2 Answers   RR,


Categories
  • Civil Engineering Interview Questions Civil Engineering (5085)
  • Mechanical Engineering Interview Questions Mechanical Engineering (4451)
  • Electrical Engineering Interview Questions Electrical Engineering (16632)
  • Electronics Communications Interview Questions Electronics Communications (3918)
  • Chemical Engineering Interview Questions Chemical Engineering (1095)
  • Aeronautical Engineering Interview Questions Aeronautical Engineering (239)
  • Bio Engineering Interview Questions Bio Engineering (96)
  • Metallurgy Interview Questions Metallurgy (361)
  • Industrial Engineering Interview Questions Industrial Engineering (259)
  • Instrumentation Interview Questions Instrumentation (3014)
  • Automobile Engineering Interview Questions Automobile Engineering (332)
  • Mechatronics Engineering Interview Questions Mechatronics Engineering (97)
  • Marine Engineering Interview Questions Marine Engineering (124)
  • Power Plant Engineering Interview Questions Power Plant Engineering (172)
  • Textile Engineering Interview Questions Textile Engineering (575)
  • Production Engineering Interview Questions Production Engineering (25)
  • Satellite Systems Engineering Interview Questions Satellite Systems Engineering (106)
  • Engineering AllOther Interview Questions Engineering AllOther (1379)