What are the deshuttering time for
Salb
Beam
Column
RCC Wall
Footing
Staircase
Answers were Sorted based on User's Feedback
Answer / tanmay
For columns, walls, vertical form works : 16-24 hrs
Soffit formwork to slabs : 3 days (props to be refixed after removal)
Soffit to beams props : 7 days props to refix after removal.
Spanning up to 4.50m : 7 days
Spanning over 4.50m : 14 days
Staircase : 5 days
Footing : 16-24 hours
| Is This Answer Correct ? | 126 Yes | 8 No |
Answer / hany
Beam sides- 24 hrs.
Beam(spanning upto 3mtrs) bottom- 10 days
Beam(spanning more than 3mtrs) bottom- 21 days
slab (spanning upto 3mtrs)- 7 days
Slab (spanning more than 3mtr)- 14 days
rcc wall- 24 hrs
Footing- 24 hrs
Staircase soffit- 7 days
| Is This Answer Correct ? | 40 Yes | 10 No |
Answer / b m sarwe
Beams 21 days
beams side 1 day after casting
slab 7-14 days
columns 1 day after casting
wall 1 day after casting
footing casting next day
Deshuttering works
| Is This Answer Correct ? | 8 Yes | 2 No |
Answer / swadesh
aprox 7 Days for Slab (If RCC used from Batching Plant)
| Is This Answer Correct ? | 13 Yes | 10 No |
Answer / farhat abbas naqvi
For deshuttering any concrete structure after pour to take in note the climate and design mix. For columns and beams sizes plays the major role. Usage of flyash also plays role in settling time.
| Is This Answer Correct ? | 4 Yes | 2 No |
Answer / h r mishra
Slab 7 days
Beam 10 days
wall, footings 24 hours
| Is This Answer Correct ? | 5 Yes | 5 No |
Answer / kirishnasekar m
all sides - next day itself (24 hours)
slab < 4.5 m-7 days
slab > 4.5 m-14 days
beam & arches < 6.0 m-14 days
beam & arches > 6.0 m-21 days
staircase waist-7days, after removal of shutter, props to be fixed for 3 days
| Is This Answer Correct ? | 0 Yes | 0 No |
Answer / simon nagaiya
Formwork Removal Time
-------------------------------
Sides of Walls, Columns and Vertical faces of beam - 24 hours to 48 hours (as per engineer’s decision)
Slabs (props left under) - 3 days
Beam soffits (props left under) - 7 days
*Removal of Props of Slabs:*
i)Slabs spanning up to 4.5m - 14 days
ii)Slabs spanning over 4.5m - 14 days
*Removal of props for beams and arches*
i)Span up to 6m - 14 days
ii)Span over 6m - 21 days
| Is This Answer Correct ? | 3 Yes | 4 No |
Answer / krishan
slab-7days
columan-24hours
beam bottom-3days
beam side-24hours
rcc wall-48hours
footing-12hours
staircase-7days
| Is This Answer Correct ? | 6 Yes | 9 No |
Answer / md.khorshed alam
slab-14days
columan-24hours
beam bottom-7days
beam side-24hours
rcc wall-48hours
footing-12hours
staircase-7days
| Is This Answer Correct ? | 1 Yes | 4 No |
What is pre-stressed concrete?
how much cement consumption in box type waterproofing
how does I measure the unit weight of steel?
what is stress
what is the exact dia of 8swg and 10swg gabion wire
What Is the Thumb rule to calculate depth and dia of pile required to carry specified load on differeent soil
what is the formular for measuring minimum depth of a foundation
what is a exact size of a cube?
how to conversation of all construction material in to brass
hi guys what happens if you are absent for a supplymentry exam?
shape of aggregates used in concrete should be rounded/cubical or elongated/flaky.
WHAT IS THE RATIO OF CEMENT:SAND:COARSE AGGREGADE IN M-20, M-25, M-30, M-35, M-40, M-45, M-50 CONCRETE?
Civil Engineering (5086)
Mechanical Engineering (4456)
Electrical Engineering (16639)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)