What are the deshuttering time for
Salb
Beam
Column
RCC Wall
Footing
Staircase
Answer Posted / h r mishra
Slab 7 days
Beam 10 days
wall, footings 24 hours
| Is This Answer Correct ? | 5 Yes | 5 No |
Post New Answer View All Answers
what are the strength theories for yeilding and fracture materials. state the theory more suited for 1. mild steel or 2. concrete
what is Brest Wall?
WHERE CAN I GET THE PREVIOUS QUESTION PAPERS OF APGENCO FOR THE THE POST OF Tr.ASSISTANT ENGINEER(CIVIL)
what is the hanekom repairing material after concreting work
WHAT THREE SPECFIC JOB POSITIONS TO YOU TARGET FROM THE COMPANY?
Need help in designing a degasser tower for 2m3/hr DM plant, also send me the formulae used
How much cement,sand,bricks and water needed for 1square metre brick work?
What do you mean by the word 'shear'?
why +1 to be followed for calculating the no of bars in BBS. Please explain
length where bent up is made in slab of bridge from one end
What are segregation and bleeding?
How much cement and water required for cement selery????
How to marking the building
The 4 main factors to start a construction project are––
why we are using stub column..? is it possible to construct steel stub column..?