Golgappa.net | Golgappa.org | BagIndia.net | BodyIndia.Com | CabIndia.net | CarsBikes.net | CarsBikes.org | CashIndia.net | ConsumerIndia.net | CookingIndia.net | DataIndia.net | DealIndia.net | EmailIndia.net | FirstTablet.com | FirstTourist.com | ForsaleIndia.net | IndiaBody.Com | IndiaCab.net | IndiaCash.net | IndiaModel.net | KidForum.net | OfficeIndia.net | PaysIndia.com | RestaurantIndia.net | RestaurantsIndia.net | SaleForum.net | SellForum.net | SoldIndia.com | StarIndia.net | TomatoCab.com | TomatoCabs.com | TownIndia.com
Interested to Buy Any Domain ? << Click Here >> for more details...

What are the deshuttering time for
Salb
Beam
Column
RCC Wall
Footing
Staircase

Answer Posted / h r mishra

Slab 7 days
Beam 10 days
wall, footings 24 hours

Is This Answer Correct ?    5 Yes 5 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

How much of the strength of concrete comes from post- production curing?

3213


What is M40 _ TOR - EQ and B.F.S

2489


procedure for preliminary selection of size of column of 5 storey building

3258


psc girder detail

3185


What is difference between code and standard and specification?

2395


how to calculate the length diamond shaped striupps in column

2768


For the calculation of bearing pressure below the footing, to know whether it is below the safe bearing pressure of the soil, the unit of RCC below ground level to be taken is 25 KN/m3 or (25-15)KN/m3, where 25 is the unit weight of RCC and 15 is the unit weight of soil and whether the weight of backfilling to be taken?

2303


mix design procedure for 1:6 cement mortar

2244


How to cal. The weight of hollow pipe?

1229


how to calculate testing date

1691


please what are the required bars for a beams of 6mx6m and 450x300mm, one is continuous and the the second is discontinuous ..Its a commercial building (church)

1833


What is .Dwg?

1306


what is the types of door's wood?

2099


1) a)to prepare mortar for bricklaying how much amount of water should be added for its maximum strength and workability(to avoid cracks which results, when high quantity of water is added)?is their a formula or ratio? b) suppose we want to make 1:3 mortar,what is the best way to measure cement ,sand and water and how? c)time before which freshly prepared mortar should be used? d)proper way to mix and make mortar? e)when should curing start after laying bricks and for how long?and also how many hours per day? f)what is shear wall (please in terms of layman lol) bookish definisions are confusing.... g) and last,acc to codes what are max no. of course that should be laid in a day.

2132


What are the ingredients of pre-stressed concrete?

1241