Golgappa.net | Golgappa.org | BagIndia.net | BodyIndia.Com | CabIndia.net | CarsBikes.net | CarsBikes.org | CashIndia.net | ConsumerIndia.net | CookingIndia.net | DataIndia.net | DealIndia.net | EmailIndia.net | FirstTablet.com | FirstTourist.com | ForsaleIndia.net | IndiaBody.Com | IndiaCab.net | IndiaCash.net | IndiaModel.net | KidForum.net | OfficeIndia.net | PaysIndia.com | RestaurantIndia.net | RestaurantsIndia.net | SaleForum.net | SellForum.net | SoldIndia.com | StarIndia.net | TomatoCab.com | TomatoCabs.com | TownIndia.com
Interested to Buy Any Domain ? << Click Here >> for more details...


What are the deshuttering time for
Salb
Beam
Column
RCC Wall
Footing
Staircase

Answers were Sorted based on User's Feedback



What are the deshuttering time for Salb Beam Column RCC Wall Footing Staircase ..

Answer / rajesh.d.v.s.p.

for columns=1day
for beams and slabs=14 days
rcc walls= 1day
fotting 1day
stair case=7 days

Is This Answer Correct ?    2 Yes 6 No

What are the deshuttering time for Salb Beam Column RCC Wall Footing Staircase ..

Answer / khiladi

14 days

Is This Answer Correct ?    16 Yes 23 No

What are the deshuttering time for Salb Beam Column RCC Wall Footing Staircase ..

Answer / atul bharadwaj

salb-1 second
beam 2 light year
column-no need of shuttering(use pre cast columns)
i dont know what is rcc wall
footing-30 years
staircase-in one storey building there is no staircase

Is This Answer Correct ?    14 Yes 87 No

Post New Answer

More Civil Engineering Interview Questions

Approximate weight of a modular brick?

2 Answers  


usually hand broken stones are used for cement concrete 1:4:8 in foundation of single /two story houses with a view of economy in construction.what advantages it will give if you use machine crushed stone in place?

0 Answers  


does the compressive strength of brick be more then 3.5 n/mm2 or 5 n/mm2?

3 Answers   L&T, Modi Builders,


what are the basic parameters considered in designing a pavement?

5 Answers  


WHAT WII BE THE WATER ABSORPTION POWER OF WOOD ?

0 Answers  


I am doing a engineering contract with GOI. I have purchased certain material from outside Maharashtra and paid CST on that material @ 5.25%. Please intimate whether I will be liable for VAT or VAT on works contract or not.

0 Answers   MES,


whaat is the difference between opc and ppc

3 Answers  


how to take the quantity of block work and plastering  1block price:3saudi riyal cement:1bag:15 saudi riyal sand:3bag:20 saudi riyal 1mason:9hour per hour 40 saudi riyal 1labour:9hour per hour 40 saudi riyal can anybdy calculate

0 Answers  


With reference to construction of state highways, please let me know the total Bill Of Quantities as per the following details:- 1) Subgrade - 500 mm 2) Granular Sub-Base (GSB) - 200 mm 3) Wet Mix Macadam I (WMM I) - 150 mm 4) Wet Mix Macadam II (WMM II) - 100 mm 5) Dense Bituminous Macadam (DBM) - 60 mm 6) Bituminous Crust (BC) - 40 mm Road Length is 44 Kms. Road Width is 7 mtrs. Please provide the BOQ of each layer as per Compacted Factor & Loose Factor both. Also, if possible please provide me the approximate details of total material required (all categories viz. soil, gravel, stone aggregrate, sand, bitumen etc.) as per general mix design prevailing in India. Thanks & Regards -- Rokr

0 Answers   Power Plant,


What is the meaning of Fe415 ?

6 Answers   Arul Constructions, L&T, SSM,


Kindly furnish the relation between 7 days strength & 28 days compressive strength of Cement Concrete cubes. Can you clarify whether the relation gets altered due to WATER- CEMENT ratio?

3 Answers  


Why use of fly ash in cement

4 Answers  


Categories
  • Civil Engineering Interview Questions Civil Engineering (5086)
  • Mechanical Engineering Interview Questions Mechanical Engineering (4456)
  • Electrical Engineering Interview Questions Electrical Engineering (16639)
  • Electronics Communications Interview Questions Electronics Communications (3918)
  • Chemical Engineering Interview Questions Chemical Engineering (1095)
  • Aeronautical Engineering Interview Questions Aeronautical Engineering (239)
  • Bio Engineering Interview Questions Bio Engineering (96)
  • Metallurgy Interview Questions Metallurgy (361)
  • Industrial Engineering Interview Questions Industrial Engineering (259)
  • Instrumentation Interview Questions Instrumentation (3014)
  • Automobile Engineering Interview Questions Automobile Engineering (332)
  • Mechatronics Engineering Interview Questions Mechatronics Engineering (97)
  • Marine Engineering Interview Questions Marine Engineering (124)
  • Power Plant Engineering Interview Questions Power Plant Engineering (172)
  • Textile Engineering Interview Questions Textile Engineering (575)
  • Production Engineering Interview Questions Production Engineering (25)
  • Satellite Systems Engineering Interview Questions Satellite Systems Engineering (106)
  • Engineering AllOther Interview Questions Engineering AllOther (1379)