What are the deshuttering time for
Salb
Beam
Column
RCC Wall
Footing
Staircase
Answer Posted / kirishnasekar m
all sides - next day itself (24 hours)
slab < 4.5 m-7 days
slab > 4.5 m-14 days
beam & arches < 6.0 m-14 days
beam & arches > 6.0 m-21 days
staircase waist-7days, after removal of shutter, props to be fixed for 3 days
Is This Answer Correct ? | 0 Yes | 0 No |
Post New Answer View All Answers
Name the main components of a cad gui?
how much to get of BRC lapping in full yield and half yield ?
WHAT IS THE % OF CONCRETE WASTAGES PERMITED IN A LARGE PROJECT ? AND WHICH IS CODE TO BE REFERED.
Which tests are performed on soil to decide the type of foundation to be provided.
how to shuttering is used in slab
What are the different types of civil engineering?
What things you need to take care of before building a kitchen island?
What in your opinion makes you the most suitably qualified candidate for this post of civil engineering technician?
What are the govt approvals required for starting of power project. means from initial site grading and excavation work.exm. blasting in hard rock, deep excavation, cut off trees from site.
as per is code, what is the minimum content of opc and ppc cement for rcc structure
How to calculate the load of partion in flat slab if we use brick?
Hi.. Can i get hel in finding HPCL previous year question paper? plz help me in finding thiss..
What tor stands for in tor steel?
how much of the strength comes from post-production curing
i want texture painting pwd data