What are the deshuttering time for
Salb
Beam
Column
RCC Wall
Footing
Staircase
Answer Posted / b m sarwe
Beams 21 days
beams side 1 day after casting
slab 7-14 days
columns 1 day after casting
wall 1 day after casting
footing casting next day
Deshuttering works
| Is This Answer Correct ? | 8 Yes | 2 No |
Post New Answer View All Answers
SAND AND STONE AGGREGATES WASTAGE PERCENTAGE IN CONCRETING WORK?
How to calculate chejja reinforcement
List out the potential risk factors for workers on the construction site?
How its coming concrete grade M 20 means 1:2:4. how it coming 1:2:4.
Explain what is zoning permit?
what is difference between NP2 NP3 NP4 CONCRETE HUME PIPES USED AT SITE
For The preparation of goverment examination Which book i will prefer and by which way i will do the preparation for exam.
What is the minimum size of the particles of silt soil?
very simple or less time consuming formula for reinforcement calculation by moment
strength of bitumen concrete with 80-100 & 60-70 grade bitumen
what is yield and tensile strength of steel, if steel has yeilding strength of 60 psi than how much its tensile strength?
what is right & short method of measurement of slab&beam
how much used soil in 1 brick of standard size?
TO CONSTRUCT A 1800 SQFT CAPACITY UNDERGROUND WATER TANK HOW MUCH CUFT CONCRETE IS REQUIRED AND HOW MUCH REINFORCEMENT IS REQUIRED. FOR COSTING
How to calculate the load of partion in flat slab if we use brick?