What are the deshuttering time for
Salb
Beam
Column
RCC Wall
Footing
Staircase

Answer Posted / b m sarwe

Beams 21 days
beams side 1 day after casting
slab 7-14 days
columns 1 day after casting
wall 1 day after casting
footing casting next day
Deshuttering works

Is This Answer Correct ?    8 Yes 2 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

for G+2 residential building how much quantity of required in foundations,sub & superstructures per sq ft area

1870


what is floating slab foundation?

639


What is Time period of a building and its relation with frequency ?

718


how to calculate the steel in 500yard

1865


Explain what is the difference between built area and super built up area?

656






how to calculate 1:5:8 ratio concrete cement, sand, metal and water please give me brief calculation

1186


what is the Asfalt test?in road constraction..?

1622


in block masonry l=10',b=0.5',H=10',Calculate cement ,sand and no.Of blocks?

1534


What is Rankine Cycle?

640


Scaffolding IS code NO.

1755


what is the formula for Mass of cement grout (Dg)=???

1711


what is raft foundation

1106


pls mail some more tecnical qustions at msaranya2610@gmail.com

1668


If we are providing concrete joint in every 10m with water stopper in water tank wall then is it necessary to cut the steel at joint section?

1355


What is alternate bid?

686