What are the deshuttering time for
Salb
Beam
Column
RCC Wall
Footing
Staircase
Answer Posted / swadesh
aprox 7 Days for Slab (If RCC used from Batching Plant)
| Is This Answer Correct ? | 13 Yes | 10 No |
Post New Answer View All Answers
What is standard Sand? What is Regime condition? What do you mean by the core trench in Earthen Dasm? What is soundness test for cement? When negetive shear force takes place in a R.C.C member?
How to design 12*12*14 room having rrc slab ,coloum, beam,foundation?
Is it possible to make a feature using an overdefined sketch?
Which prize is the alternative to the NOVEL Prize?
What are wooden shingles?
The portion of a brick cut across the width is called?
how many spacers we need for 1 ton reinforcement? aprox.
Used Cement & Sand in 1 Square Meter or 1 Square Feet For Brick Work 0.115mm ? (1:4) (1:6)
How to find beam R/F cutting length
How reactor of SBR installed , is it be over ground, fully under ground or semi sunk ?
Which Types Of Bricks ?
Bearing capacity of soil determined as per ASTM is to design the foundation size.what is the importance of EV1/EV2 value as per DIN .My consultant ask me to test the the soil as per din to find out this ratio to assess the compacted strength of soil ,,?? is it meaning full ??
What Is the Thumb rule to calculate depth and dia of pile required to carry specified load on differeent soil
whats is difference between anchorage length and development length
I want some common questions which have been asked in interviews of NTPC Limited,Satluj Jal Vidyut Nigam Ltd.,and Bharat Heavy Electricals Ltd.