What are the deshuttering time for
Salb
Beam
Column
RCC Wall
Footing
Staircase

Answer Posted / tanmay

For columns, walls, vertical form works : 16-24 hrs
Soffit formwork to slabs : 3 days (props to be refixed after removal)
Soffit to beams props : 7 days props to refix after removal.
Spanning up to 4.50m : 7 days
Spanning over 4.50m : 14 days
Staircase : 5 days
Footing : 16-24 hours

Is This Answer Correct ?    126 Yes 8 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

What is the use of mirror command?

744


How Can I know the wastages(%) of each work added in estimating the quantity of construction materials?(Eg. Ceiling Work, Brick Work,etc....)

1498


Who name us Engineer & Why?

2021


how to tie 10 legged stirrups

5875


What are the phases inspections are done by local authority while construction?

708






how can we calculate steel value, depending on load

1730


in the construction of residential building what type of tank are used?where?why & what is its purpose?

1897


how much cement and sand consuptin in 4 inch siporex walls 100 sq ft

2493


silt%= silt volume/ silt+sand volume is this right?

1496


Use of coping on terrace wall and in 4" wall is compulsory or not ?

1089


How will you reduce the concrete flow after mixing the concrete

1711


what is the weight of 12mm aggregates?

1084


how to caluclate sienerge qty in construction in ap

1889


a solid steel rod length 2m dia and 20mm vertically hangs from celling and has a collar firmly atteched to it. above the collar an annular rubber washer of 40mm th. having stifness k = 5n/mm is placed. determine maximum stress in the rod caused by mass of 5 kg falling through a height of 1.2m.

1863


What is the density of most of construction materials?

720