What are the deshuttering time for
Salb
Beam
Column
RCC Wall
Footing
Staircase
Answer Posted / tanmay
For columns, walls, vertical form works : 16-24 hrs
Soffit formwork to slabs : 3 days (props to be refixed after removal)
Soffit to beams props : 7 days props to refix after removal.
Spanning up to 4.50m : 7 days
Spanning over 4.50m : 14 days
Staircase : 5 days
Footing : 16-24 hours
| Is This Answer Correct ? | 126 Yes | 8 No |
Post New Answer View All Answers
Sometimes the side of concrete bridges is observed to turn black in color. What is the reason for this phenomenon?
what mean By core Billing
What are the important hardware systems used for cad?
Write short note on construction programme for pile foundation.
Explain what is the difference between built area and super built up area?
How much does it cost for a R.C.C cover slab of size (450mmX 600mmx 100mm) double rf net given in feets using hand mix concrete?
a sewer which receives the discharge of no. of house sewer is called house sewer lateral sewer intrcepting sewer sub-main sewer
My daily concrete volume of M25 concrete is 1st day= 25 Cum 2nd Day = 45 Cum 3rd Day = 55 Cum 4th Day = 22 Cum 5th Day =72 Cum 7th Day = 49 Cum. What will be acceptance criteria of concrete considering as per is 456 cl.15 and table 11 (cl 16.1 and 16.3).
What in your past experience or education prepares you for the position for which you are applying
what is high type road and low type roads
a butt weld is specified by
What is meaning of FREE STANDING STAIRCASE ?
que.is ideal size of bricnk use in india,joint size of mortar in massinary ,how many bricks used in 1cum.how to test at site.what is the possition of marka used in bricks?
What are the different theories of failure under static load?
How much sand and cement requirement for 1 SQM 125mm thickness Brickwork