What are the deshuttering time for
Salb
Beam
Column
RCC Wall
Footing
Staircase
Answer Posted / tanmay
For columns, walls, vertical form works : 16-24 hrs
Soffit formwork to slabs : 3 days (props to be refixed after removal)
Soffit to beams props : 7 days props to refix after removal.
Spanning up to 4.50m : 7 days
Spanning over 4.50m : 14 days
Staircase : 5 days
Footing : 16-24 hours
Is This Answer Correct ? | 126 Yes | 8 No |
Post New Answer View All Answers
What is the use of mirror command?
How Can I know the wastages(%) of each work added in estimating the quantity of construction materials?(Eg. Ceiling Work, Brick Work,etc....)
Who name us Engineer & Why?
how to tie 10 legged stirrups
What are the phases inspections are done by local authority while construction?
how can we calculate steel value, depending on load
in the construction of residential building what type of tank are used?where?why & what is its purpose?
how much cement and sand consuptin in 4 inch siporex walls 100 sq ft
silt%= silt volume/ silt+sand volume is this right?
Use of coping on terrace wall and in 4" wall is compulsory or not ?
How will you reduce the concrete flow after mixing the concrete
what is the weight of 12mm aggregates?
how to caluclate sienerge qty in construction in ap
a solid steel rod length 2m dia and 20mm vertically hangs from celling and has a collar firmly atteched to it. above the collar an annular rubber washer of 40mm th. having stifness k = 5n/mm is placed. determine maximum stress in the rod caused by mass of 5 kg falling through a height of 1.2m.
What is the density of most of construction materials?