What are the deshuttering time for
Salb
Beam
Column
RCC Wall
Footing
Staircase
Answer Posted / md.khorshed alam
slab-14days
columan-24hours
beam bottom-7days
beam side-24hours
rcc wall-48hours
footing-12hours
staircase-7days
Is This Answer Correct ? | 1 Yes | 4 No |
Post New Answer View All Answers
How to calculate the area of a irregular sized land in square feet?and what will be the total area of this land South-51.1ft , North-47.7ft , East-53.3ft , West-54ft ?please explain me how to calculate?
Define What is an ice dam sock?
What is the cost of shuttering per Sqm.? How it is calculate by thumb rule...?
can i get hindi version of is codes based on civil engineering?
afe or not
kindly mail me by attaching files , formats for quality checks of common building materials like cement , concrete , bricks , sand and aggregates plz send my email id- VMANDAL91@gmail.com
How is the leaning tower of pisa supported?
what is polity
What is meant by scaffolding coefficient?
What should be the maximum allowable time for placing ready mix concrete? The specification requires concrete placement within 90 minutes of batching at the plant. What is the significance of this 90 minutes & should this be used as a rejection criterion? What effects does the concrete has after that time period?
what is the anchorage length of reinforcement.
60-70 grade of Bitumen is VG-30 ?
Explain the mechanism of cavitations in pipes and drains?
What are the applications of cad?
What is high adherence steel bar? I have a general specification which refers to High Adherence steel bars, coils and meshes to BS EN 10080 and BS 4449 or BS 4483. Is this just general re-bar or is there something different about it? The spec originated in France.