What are the deshuttering time for
Salb
Beam
Column
RCC Wall
Footing
Staircase
Answer Posted / md.khorshed alam
slab-14days
columan-24hours
beam bottom-7days
beam side-24hours
rcc wall-48hours
footing-12hours
staircase-7days
| Is This Answer Correct ? | 1 Yes | 4 No |
Post New Answer View All Answers
a) we have 30nos., 300mm dia, 4m length double under reamed piles.calculate excavation quantity.b) tell concrete qty. also.
does a b.tech civil engineer fresher supposed to know how to design rcc structure?
SAND AND STONE AGGREGATES WASTAGE PERCENTAGE IN CONCRETING WORK?
what is the difference between natural draught cooling tower and induced draught cooling tower
std penetration resistance in very stiff clays lies bet 2 & 4 4 & 8 8 & 15 15 & 30
What things you need to take care of before building a kitchen island?
what is the theoritical percentage of concrete cubes testing per day?
What is difference between engineering stress and true stress?
for 32 dia (EQR HYSD steel) bar how much deduction for 45 and 90 degree band
What do you mean by bond? What are the different types of bonds?
What is the largest concrete dam in the world?
What is semirigid connections?
what is the percentage of silt in black cotton soil.?
the magnitude of the buoyant force can be determine by newtons law of viscosity archimidies principal principles of momemnt none
How to come 1.54 from dry to wet concrete?