How to calculate the amount of Brick,cement & sand required
for 1 cum of 230mm thick brick work with ratio 1:5 please
give me an answer with detailed step

Answers were Sorted based on User's Feedback



How to calculate the amount of Brick,cement & sand required for 1 cum of 230mm thick brick work..

Answer / suresh k

Bricks 500 no.
Cement 1.6 bags
Sand 0.3 cub-meter

Is This Answer Correct ?    0 Yes 1 No

How to calculate the amount of Brick,cement & sand required for 1 cum of 230mm thick brick work..

Answer / sai ganneshh

sand=0.20cum(1cum*0.20=0.20cum)
1 cum cement= 0.20*1440/ratio last digit
if(1:5) cement =0.20*1440/5=57.6kgs
1 bag =50kg
(57.7/50=1.154bags)

Is This Answer Correct ?    0 Yes 1 No

How to calculate the amount of Brick,cement & sand required for 1 cum of 230mm thick brick work..

Answer / satinder singh

brick size= .230*.115*.75
1/.230*.115*.75 = 500
10 mm mortar consider now our brick size is .240*.125*.85
1/.240*.125*.85 =500
392 = 500
500-392= 108 bricks
now 108*0.00255 = 0.275 cu m
for mortar 1:6
cement = 1/7*0.275 = 0.0393/0.0345 = 1.13 bag
sand = 6/7*0.275 = 0.023 cu m

Is This Answer Correct ?    1 Yes 2 No

How to calculate the amount of Brick,cement & sand required for 1 cum of 230mm thick brick work..

Answer / gulshan vashisht from hassanpu

brick = 476 (as pr calculation)
.3= dry volume of brick mortar
cement = .3*28.8/total of ratio(6)
= 1.44 begs in one cum
sand = .3*quantity of sand(5)/total of ratio
= .250 for one cum

Is This Answer Correct ?    5 Yes 7 No

How to calculate the amount of Brick,cement & sand required for 1 cum of 230mm thick brick work..

Answer / neelesh chouhan

Bricks = 500 no.
cement = 1.762
sand = 0.306 cum

Is This Answer Correct ?    10 Yes 12 No

How to calculate the amount of Brick,cement & sand required for 1 cum of 230mm thick brick work..

Answer / neelesh chouhan

Bricks = 500 no.
cement = 1.762 beg
sand = 1.836 cum

Is This Answer Correct ?    6 Yes 8 No

How to calculate the amount of Brick,cement & sand required for 1 cum of 230mm thick brick work..

Answer / selvaraju

brick = 390 nos as per construction
sand = 0.30m3
cement= 1.90 bags

Is This Answer Correct ?    5 Yes 7 No

How to calculate the amount of Brick,cement & sand required for 1 cum of 230mm thick brick work..

Answer / sheraz

No of Bricks= volume of total brickwork / volume of brick= 1 / 0.002 =500 NO.s
Volume of mortar is 30% of volume of brickwork = 0.30 cum
dry volume of mortar = 0.30 x 1.54 = 0.462 cum
So cement Quantity = 1x0.462/1+5 = 0.077 cum
divide it by the volume of cement bag that is 0.0347 = 0.077 / 0.0347 = 2.22 bags
sand quantity = 5 x 0.462 / 1+5 = 0.385 cu m

Is This Answer Correct ?    0 Yes 2 No

How to calculate the amount of Brick,cement & sand required for 1 cum of 230mm thick brick work..

Answer / brajesh rai

brick 500
cement 1.6 bags
sand 0301 m3

Is This Answer Correct ?    8 Yes 11 No

How to calculate the amount of Brick,cement & sand required for 1 cum of 230mm thick brick work..

Answer / bhupendra singh panwar

.230*1*1=.230
dry mortar 30%
.069/6=0.0115
cement= .35 beg
sand  =.0575 cum
brick =115 nos.

Is This Answer Correct ?    0 Yes 6 No

Post New Answer

More Civil Engineering Interview Questions

which type of foundation are most prefarable in blockcotton soils

3 Answers   IVRCL,


What is cutting Length of stirrups of a beam 300mm*300mm.

3 Answers  


what is thumb rule for calculating the size of ISMB required for a particular length of span

0 Answers  


Is there is any formula for calculate the correct length of rebar while it bending in 45 degree/90 degree and cranking???

2 Answers   L&T, NBCC,


What should be the Min.Penetration in a hard rock for all pile diameteres?

1 Answers  






. Write a C program to perform following functions:- a. Declare one integer variable of all the storage classes. b. Print all the variables without assigning any values in tabular format. a. The tabular format must contain the variable name, type, storage class and printed value on the screen in RED color.

0 Answers  


Please provide detail I.S standard code for using crush sand instead of river sand for plaster and concrete grade M15, M20, M25 and M30 and its mix design

1 Answers   JPMorgan Chase, Sobha Developers, Structwel,


what is mean by shear resistance in concrete?

3 Answers   CCCL, Noble Consolidated Glazings, Sobha Developers,


What is the withdrawal force of steel nails?

0 Answers  


if i have to draw bending moment diagram of 4 way continous span then how to create it and how to find reaction?

0 Answers  


Please tell me vasthu room sizes. Thanks.

0 Answers  


How we calculate the cement for the M 15 normal concrete with aggregate size is 40 mm ?

5 Answers   Madhucon,


Categories
  • Civil Engineering Interview Questions Civil Engineering (5085)
  • Mechanical Engineering Interview Questions Mechanical Engineering (4451)
  • Electrical Engineering Interview Questions Electrical Engineering (16632)
  • Electronics Communications Interview Questions Electronics Communications (3918)
  • Chemical Engineering Interview Questions Chemical Engineering (1095)
  • Aeronautical Engineering Interview Questions Aeronautical Engineering (239)
  • Bio Engineering Interview Questions Bio Engineering (96)
  • Metallurgy Interview Questions Metallurgy (361)
  • Industrial Engineering Interview Questions Industrial Engineering (259)
  • Instrumentation Interview Questions Instrumentation (3014)
  • Automobile Engineering Interview Questions Automobile Engineering (332)
  • Mechatronics Engineering Interview Questions Mechatronics Engineering (97)
  • Marine Engineering Interview Questions Marine Engineering (124)
  • Power Plant Engineering Interview Questions Power Plant Engineering (172)
  • Textile Engineering Interview Questions Textile Engineering (575)
  • Production Engineering Interview Questions Production Engineering (25)
  • Satellite Systems Engineering Interview Questions Satellite Systems Engineering (106)
  • Engineering AllOther Interview Questions Engineering AllOther (1379)