How to calculate the amount of Brick,cement & sand required
for 1 cum of 230mm thick brick work with ratio 1:5 please
give me an answer with detailed step
Answers were Sorted based on User's Feedback
Answer / suresh k
Bricks 500 no.
Cement 1.6 bags
Sand 0.3 cub-meter
Is This Answer Correct ? | 0 Yes | 1 No |
Answer / sai ganneshh
sand=0.20cum(1cum*0.20=0.20cum)
1 cum cement= 0.20*1440/ratio last digit
if(1:5) cement =0.20*1440/5=57.6kgs
1 bag =50kg
(57.7/50=1.154bags)
Is This Answer Correct ? | 0 Yes | 1 No |
Answer / satinder singh
brick size= .230*.115*.75
1/.230*.115*.75 = 500
10 mm mortar consider now our brick size is .240*.125*.85
1/.240*.125*.85 =500
392 = 500
500-392= 108 bricks
now 108*0.00255 = 0.275 cu m
for mortar 1:6
cement = 1/7*0.275 = 0.0393/0.0345 = 1.13 bag
sand = 6/7*0.275 = 0.023 cu m
Is This Answer Correct ? | 1 Yes | 2 No |
Answer / gulshan vashisht from hassanpu
brick = 476 (as pr calculation)
.3= dry volume of brick mortar
cement = .3*28.8/total of ratio(6)
= 1.44 begs in one cum
sand = .3*quantity of sand(5)/total of ratio
= .250 for one cum
Is This Answer Correct ? | 5 Yes | 7 No |
Answer / neelesh chouhan
Bricks = 500 no.
cement = 1.762
sand = 0.306 cum
Is This Answer Correct ? | 10 Yes | 12 No |
Answer / neelesh chouhan
Bricks = 500 no.
cement = 1.762 beg
sand = 1.836 cum
Is This Answer Correct ? | 6 Yes | 8 No |
Answer / selvaraju
brick = 390 nos as per construction
sand = 0.30m3
cement= 1.90 bags
Is This Answer Correct ? | 5 Yes | 7 No |
Answer / sheraz
No of Bricks= volume of total brickwork / volume of brick= 1 / 0.002 =500 NO.s
Volume of mortar is 30% of volume of brickwork = 0.30 cum
dry volume of mortar = 0.30 x 1.54 = 0.462 cum
So cement Quantity = 1x0.462/1+5 = 0.077 cum
divide it by the volume of cement bag that is 0.0347 = 0.077 / 0.0347 = 2.22 bags
sand quantity = 5 x 0.462 / 1+5 = 0.385 cu m
Is This Answer Correct ? | 0 Yes | 2 No |
Answer / bhupendra singh panwar
.230*1*1=.230
dry mortar 30%
.069/6=0.0115
cement= .35 beg
sand =.0575 cum
brick =115 nos.
Is This Answer Correct ? | 0 Yes | 6 No |
which type of foundation are most prefarable in blockcotton soils
What is cutting Length of stirrups of a beam 300mm*300mm.
what is thumb rule for calculating the size of ISMB required for a particular length of span
Is there is any formula for calculate the correct length of rebar while it bending in 45 degree/90 degree and cranking???
What should be the Min.Penetration in a hard rock for all pile diameteres?
. Write a C program to perform following functions:- a. Declare one integer variable of all the storage classes. b. Print all the variables without assigning any values in tabular format. a. The tabular format must contain the variable name, type, storage class and printed value on the screen in RED color.
Please provide detail I.S standard code for using crush sand instead of river sand for plaster and concrete grade M15, M20, M25 and M30 and its mix design
1 Answers JPMorgan Chase, Sobha Developers, Structwel,
what is mean by shear resistance in concrete?
3 Answers CCCL, Noble Consolidated Glazings, Sobha Developers,
What is the withdrawal force of steel nails?
if i have to draw bending moment diagram of 4 way continous span then how to create it and how to find reaction?
Please tell me vasthu room sizes. Thanks.
How we calculate the cement for the M 15 normal concrete with aggregate size is 40 mm ?