How to calculate the amount of Brick,cement & sand required
for 1 cum of 230mm thick brick work with ratio 1:5 please
give me an answer with detailed step
Answer Posted / sheraz
No of Bricks= volume of total brickwork / volume of brick= 1 / 0.002 =500 NO.s
Volume of mortar is 30% of volume of brickwork = 0.30 cum
dry volume of mortar = 0.30 x 1.54 = 0.462 cum
So cement Quantity = 1x0.462/1+5 = 0.077 cum
divide it by the volume of cement bag that is 0.0347 = 0.077 / 0.0347 = 2.22 bags
sand quantity = 5 x 0.462 / 1+5 = 0.385 cu m
| Is This Answer Correct ? | 0 Yes | 2 No |
Post New Answer View All Answers
Explain what is Critical Path Method (C.P.M)?
For fine aggregate which is most suitable River sand or crusher sand & why ?
the magnitude of the buoyant force can be determine by newtons law of viscosity archimidies principal principles of momemnt none
column at edge of a framed structure is uniaxial or biaxial. and is an interior column is biaxial
What is the biggest dam in america?
What is the diff between cad & cadd?
At one time what is the height of Lift for concreting for Bridge Piers Class B Loading and refer the code.
Describe the sections included in a typical bill of quantities
usually hand broken stones are used for cement concrete 1:4:8 in foundation of single /two story houses with a view of economy in construction.what advantages it will give if you use machine crushed stone in place?
Before casting a basement roof slab which is connected with retaining wall surcharge load (i.e. sand or earth filling) outside the retaining wall is prohibited because of––
Please tell me vasthu room sizes. Thanks.
How to do bbs in excel format
a) we have 30nos., 300mm dia, 4m length double under reamed piles.calculate excavation quantity.b) tell concrete qty. also.
Discuss some applications of modular elasticity?
why is the column design?