how do understand the plinth beam croos section diagram
Answer / sjtbehera
Most soil conditions and building loads can be managed with
normal 1:2:4 plain concrete (PCC), which is good in taking
compression.
Steel, specially reinforced, is best to tackle tension,
which does not prevail much at the wall bottom.
It's the sheer wall load that needs to be transferred to the
foundation; as such, 4” thick plinth concrete is adequate.
As a cost-effective measure, reducing plinth concrete width
to the wall thickness, say 9” only instead of it being twice
the width at 1'6” is feasible, if appropriate conditions
prevail.
Uneven settlement
If so, why are the RCC plinth beams required? In soft and
water-logged soils, if the earth settles downwards, the
plinth may face uneven settlement.
In RCC frame structure, plinth acts as a tie, as a beam at
ground level itself. More recently, after few disasters we
have faced, RCC plinth beams are being recommended for their
earthquake-resistant properties.
In case of boulder-packed foundation in loose soil, RCC
plinth is advised to ensure proper load transfers. It is
obvious then that we should not question RCC plinths, but
question their wasteful application where not necessary
| Is This Answer Correct ? | 2 Yes | 1 No |
I want to know about history of civil engineering?
what is the crushing strength of good building stone
water cement ratio
what is tensile strength of {6,8,10,12,16,20}mm dia bar? also there were any formula?
weight of 1 cft 10mm, 20mm, 40mm aggregate weight of 1cft course sand
0 Answers Tanishq, Target, Yahoo,
What is the cost of formwork for columns/beams/rcc walls also what is the cost of shuttering for roof slab at height of 25 feet
what is the difference between pumpable concrete and non pumpable concrete
can i place column steel lapping in floor beam? my lapping is 24 inches in floor beam and 24 inches on floor beam
As per IS 2502 2(A+B)+24d formula is given for stirrups detailing,but explination not given for how that 24d came
How many bages of cement used in 1cft?and how we calculat sand and agregats
How to check percentage of bulkage of sand in RCC?
how do we calculate quantity of cement , sand and aggregates in 1 m3 of M30 grade concrete ?
31 Answers ABES Engineering College, Gammon, Jalanidhi, NCC,
Civil Engineering (5086)
Mechanical Engineering (4456)
Electrical Engineering (16639)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)