How to calculate the amount of Brick,cement & sand required
for 1 cum of 230mm thick brick work with ratio 1:5 please
give me an answer with detailed step
Answers were Sorted based on User's Feedback
Answer / zuber ahmed
Volume of Dry Mortar = 35% of volume of Brickwork
Volume of Mortar required = 0.35 + 1 = 1.35 cu.m.
Cement required = 1/6 X 1.35 = 0.225 cu.m. =6.8Bags
Sand required = 5/6 X 1.35 = 1.125 cu.m.
Bricks required = 500 Nos.
Is This Answer Correct ? | 10 Yes | 43 No |
Factor of safety for steel should be based on its yield stress or its ultimate stress and factor of safety for concrete should be based on its ultimate stress or its yield stress?
What is the standard brick size in India(IS)
How can we calculate the no.of bricks per sq.mr?
3 Answers GTL, Real, Sahyadri,
What is m20 and What is 20 ?
2 Answers Sukhwani Constructions,
how to calclate the SHUTTERING TAKEN CONCRETE LOAD? WHAT IS THE LOAD BEARING CAPACITY IN STEEL SHUTTERING PLATE? WHAT IS THE CONCRETE LOAD IN (MASS) IN THE SHUTTERING PLATE. PLATE SIZE IS 120CM* 90CM CONCRETE WALL LENGTH IS 10M ,WIDE IS 60CM, HEIGHT IS 1.2M PLS TO SENT THE CALCULATION.
who to calculate the bar bending schedule?
indiploma civil engineering student r studied is456-1978. but in practicial we r using 2000 version i think 1978 version didn't use the student. any openion?
stub column means
What are the Types of foundation?
is it fair to recruit another prestressing agency once earlier agency has provided guide cone for post stressing the Concrete -I girders? It is observed that the bearing plate of another agency is not matching with the earlier one resulting in protruded strands after stressing from the face of girder. Kindly advice.
can we find any technical issue if we are gong to change the dimensions of steel beams from one type to another type IE if there are any equievelant data base to find solution for problem of changeing sectios of beam from one type to another with the same cross sectional area.
How to find permissible diagonal tensile stress in reinforced brick work