How to calculate the amount of Brick,cement & sand required
for 1 cum of 230mm thick brick work with ratio 1:5 please
give me an answer with detailed step
Answer Posted / neelesh chouhan
Bricks = 500 no.
cement = 1.762 beg
sand = 1.836 cum
| Is This Answer Correct ? | 6 Yes | 8 No |
Post New Answer View All Answers
how we calculate the vol.of wet concrete..?
Whats be the minimum foundation depth of multistoried building as per height of building in individual footing?
What are the materials used in building a gravity dam?
Pls provide me with the calculation or codes related to de- shuttering of flat slabs
roll of DLC in road constructions
I want to know about rolling margin of steel :- For eg. If 2nos. bundle of 8mm dia steel with17 rods each of length 12m comes to store. During testing of 1m rod of each bundle it was found that 1rod has weight .405kg/m while other has .385kg/m. Now what will happen in case of steel payment and measurement payment ? Regards,
Analyze the rate for 1st class brick work in superstructure with 1:6 cement sand mortar. Consider 1000 cu.ft quantity and work out the rate per cu.ft
What is soil enforcement?
How can i do RCC rate analysis?
cement, sand, aggregate,reinforcement & concrete consumption per square feet in multi storeyed building
what does the grad of cement shows (denotes)?
I want some common questions which have been asked in interviews of NTPC Limited,Satluj Jal Vidyut Nigam Ltd.,and Bharat Heavy Electricals Ltd.
what is mc arther pile?
how to calculate spacing rod in column
115mm thickness brick work how to required mortar