How to calculate the amount of Brick,cement & sand required
for 1 cum of 230mm thick brick work with ratio 1:5 please
give me an answer with detailed step

Answers were Sorted based on User's Feedback



How to calculate the amount of Brick,cement & sand required for 1 cum of 230mm thick brick work..

Answer / sriram

500nos

Is This Answer Correct ?    8 Yes 4 No

How to calculate the amount of Brick,cement & sand required for 1 cum of 230mm thick brick work..

Answer / abdurrahman

Dimention of brick=215mmx102.5mmx65mm
total volume=0.230*0.115*0.075=0.00198cum
calculate the no. of brick in 1cum= 1cum/.00198cum=505 brick
(2)calculate the cement
total dry mortar required in 1cum=0.30cum
cement required 1+5=6 0.30/6=0.05cum
cement in kg 0.05*1440=72kg
sand required=0.30*5/6=.25cum
sand required=0.25*1520=380kg

Is This Answer Correct ?    1 Yes 0 No

How to calculate the amount of Brick,cement & sand required for 1 cum of 230mm thick brick work..

Answer / arunprakash g

1) BRICK CALCULATION:

SIZE: 19x19x19 nos of brick using at cum = 500nos
500 x 6 = 3000

2)CEMENT CALCULATION:

1.75 Bags using at cum
opc 410/bag so 1.75 x 410 = Rs 720/cum

3)SAND CALCULATION:

0.25 unit/cum
river sand Rs 9000/3units so 1 unit =3000
so 0.25 x 3000 = Rs 750/cum

Is This Answer Correct ?    3 Yes 2 No

How to calculate the amount of Brick,cement & sand required for 1 cum of 230mm thick brick work..

Answer / md labib arfat

Size of brick =230mmx115mmx75mm volume of brick= 0.00198cum thickness of mortar is 10mm size of brick =240mmx125mmx85mm volume of brick =0.00255 no. Of brick in 1cum =1/0.00255 =392nos. Volume of bricks in 1cum =392x0.00198=0.77793 cement mortar required = 1-0.77763=0.22237cum add 15% for wet mix =(0.15x0.22237) 0.22237=0.255cum add 1/3 for dry volume =(0.33x0.255) 0.255=0.34cum ratio 1:5 cement required = (1x0.34)/6=0.056cum 0.056x1440=80.64 =1.6 bags sand required = (5x0.34)/6=0.283 cum

Is This Answer Correct ?    4 Yes 4 No

How to calculate the amount of Brick,cement & sand required for 1 cum of 230mm thick brick work..

Answer / arunprakash.g

brick : 500 nos

cement : 1.75 bags

sand : 0.26 units

mason : 1 mason

mazdoor : 1 men , 1 women

water : 2% of total cost.

Is This Answer Correct ?    0 Yes 0 No

How to calculate the amount of Brick,cement & sand required for 1 cum of 230mm thick brick work..

Answer / ajay padma

494 nos

Is This Answer Correct ?    0 Yes 0 No

How to calculate the amount of Brick,cement & sand required for 1 cum of 230mm thick brick work..

Answer / anil shinde

if we consider brick size 230mmx150mmx80mm thk,
requrired brick qty will -215 nos,considering mortar thkness will 12mm .

total mortar area-.407cum for 1cum area brick masonary
therefore brick area will 1cum-.407cum=.592cum

Is This Answer Correct ?    0 Yes 0 No

How to calculate the amount of Brick,cement & sand required for 1 cum of 230mm thick brick work..

Answer / vimal

Q: brick work cement cu M 0.3,
Various brick size (solids block 8"*8"*16")cu M. ?

Is This Answer Correct ?    0 Yes 0 No

How to calculate the amount of Brick,cement & sand required for 1 cum of 230mm thick brick work..

Answer / raj

Hi guys..
I need 1cu.m congrate on how many cement bags, sand ,aggrecate ( 20 mm) and water added..
M20 grade of congrate..
Plz guys answer mee...

Is This Answer Correct ?    0 Yes 0 No

How to calculate the amount of Brick,cement & sand required for 1 cum of 230mm thick brick work..

Answer / md jawed akhtar ansari

Modular Brick 500 Nos
Traditional Brick 480 Nos

Is This Answer Correct ?    7 Yes 8 No

Post New Answer

More Civil Engineering Interview Questions

Define What are the materials used in building a gravity dam?

0 Answers  


hai, kindly send anyone for output workers format details for construction project in foundation to finishing.

0 Answers  


how to calculate the circular beam reinforcement.its a helipad beam. Dia of bar 25 mm. if its consider any elongation?

1 Answers   Gammon,


please what is the number of bars required for a column of 6mx6m and 450mmx300mm,its a commercial building (Church)

0 Answers  


Dear Sir I Mahesh C. Bhamre have already given a Exam for Superintendent Officer / Public relation Officer Exam Dharmday Aaukta held at Nashik on Date 29/08/2010. My seat no was 5040247. and my cell no is 9822677994. and my mail Id is - mahesh.bhamre@rediffmail.com So can you pl send me details of result of respective exams. Thanking you in Anticipation.

0 Answers  






Is there the dry coefficient of cement is constant?

0 Answers  


In few lines, please be elaborative on extras and talents that make you a potential candidate for the post:

0 Answers  


how to disign cuplock shuttering and it's matireal requirement snd any related web site

0 Answers   DLF,


Doul Bar reinforcement and details of drawing.

0 Answers   Atlanta Infrastructure,


What is Dewatering ?

1 Answers   GreenTree,


at the beam-column junction point tell me how much beam bars should pass through column ring ? 3 or 2 or 1 . answer with reason. if it is not happen then what will be he effect ?

1 Answers  


How to calculate cut length of square shape stirrups?

5 Answers  


Categories
  • Civil Engineering Interview Questions Civil Engineering (5085)
  • Mechanical Engineering Interview Questions Mechanical Engineering (4451)
  • Electrical Engineering Interview Questions Electrical Engineering (16632)
  • Electronics Communications Interview Questions Electronics Communications (3918)
  • Chemical Engineering Interview Questions Chemical Engineering (1095)
  • Aeronautical Engineering Interview Questions Aeronautical Engineering (239)
  • Bio Engineering Interview Questions Bio Engineering (96)
  • Metallurgy Interview Questions Metallurgy (361)
  • Industrial Engineering Interview Questions Industrial Engineering (259)
  • Instrumentation Interview Questions Instrumentation (3014)
  • Automobile Engineering Interview Questions Automobile Engineering (332)
  • Mechatronics Engineering Interview Questions Mechatronics Engineering (97)
  • Marine Engineering Interview Questions Marine Engineering (124)
  • Power Plant Engineering Interview Questions Power Plant Engineering (172)
  • Textile Engineering Interview Questions Textile Engineering (575)
  • Production Engineering Interview Questions Production Engineering (25)
  • Satellite Systems Engineering Interview Questions Satellite Systems Engineering (106)
  • Engineering AllOther Interview Questions Engineering AllOther (1379)