Golgappa.net | Golgappa.org | BagIndia.net | BodyIndia.Com | CabIndia.net | CarsBikes.net | CarsBikes.org | CashIndia.net | ConsumerIndia.net | CookingIndia.net | DataIndia.net | DealIndia.net | EmailIndia.net | FirstTablet.com | FirstTourist.com | ForsaleIndia.net | IndiaBody.Com | IndiaCab.net | IndiaCash.net | IndiaModel.net | KidForum.net | OfficeIndia.net | PaysIndia.com | RestaurantIndia.net | RestaurantsIndia.net | SaleForum.net | SellForum.net | SoldIndia.com | StarIndia.net | TomatoCab.com | TomatoCabs.com | TownIndia.com
Interested to Buy Any Domain ? << Click Here >> for more details...


if my 6 kva UPS gives 20 min. backup at 100 % load, then at
25% load what is the backup time?

Answers were Sorted based on User's Feedback



if my 6 kva UPS gives 20 min. backup at 100 % load, then at 25% load what is the backup time?..

Answer / nadeem

80 mins

Is This Answer Correct ?    10 Yes 1 No

if my 6 kva UPS gives 20 min. backup at 100 % load, then at 25% load what is the backup time?..

Answer / miarcle

100% load means = 20 minutes so
25%load means 4x20minit=80 minits

Is This Answer Correct ?    10 Yes 2 No

if my 6 kva UPS gives 20 min. backup at 100 % load, then at 25% load what is the backup time?..

Answer / gopalakrishnan

50 minutes

for example let us take four fans at 100% load for 20 minutes.
100% load means 4 fans = 20 minutes
75% load means 3 fans = 30 minutes
50% load means 2 fans = 40 minutes
25% load means 1 fan = 50 minutes

Is This Answer Correct ?    6 Yes 1 No

if my 6 kva UPS gives 20 min. backup at 100 % load, then at 25% load what is the backup time?..

Answer / sathya

50 min

Is This Answer Correct ?    4 Yes 3 No

if my 6 kva UPS gives 20 min. backup at 100 % load, then at 25% load what is the backup time?..

Answer / prakash kusuma

at 25% load a 6kva UPS give back up of 50 min
as at 100% = 20 min ok
50% = 40 min
25% = 50 min (40 min + 20 min = 60 min(no load)
- 10 min(25 % load )= 50 min( back up)

Is This Answer Correct ?    1 Yes 0 No

if my 6 kva UPS gives 20 min. backup at 100 % load, then at 25% load what is the backup time?..

Answer / bibhu(bbb)

80min
100% load =20min
1% load=20*100 min
25% load=(20*100)/25min.

Is This Answer Correct ?    1 Yes 0 No

if my 6 kva UPS gives 20 min. backup at 100 % load, then at 25% load what is the backup time?..

Answer / miracle

100% load means = 20 minutes so 25%x20minit=80 minits

Is This Answer Correct ?    3 Yes 3 No

if my 6 kva UPS gives 20 min. backup at 100 % load, then at 25% load what is the backup time?..

Answer / jayesh

50 min
20min = 100% load
? = 25% load
=20*25/100
=50 min

Is This Answer Correct ?    2 Yes 2 No

if my 6 kva UPS gives 20 min. backup at 100 % load, then at 25% load what is the backup time?..

Answer / symon

80 mints

Is This Answer Correct ?    0 Yes 0 No

if my 6 kva UPS gives 20 min. backup at 100 % load, then at 25% load what is the backup time?..

Answer / s kumar

If 6 Kva UPS given 20 min. backup at 100%load
backup at (50%)100/2------20*2=40min
backup at (25%)100/4------20*4=80min

Then 80 min. Backup at 25 %load

Is This Answer Correct ?    0 Yes 1 No

Post New Answer

More Instrumentation Interview Questions

we have a s-5 simense plc having op7 .recently on op7 showing error 1.plc not present 2. DB error frequently. can u have any solution . please send me.

0 Answers  


generally transmitter power supply having some range(12v to 35v) but the out put(4-20 mA) must same for given input.If we vary the power supply voltage then output mA also to be change according to V=IR. Is there any voltage regulator in the transmitter ?

1 Answers  


What is the difference between EPROM & EEPROM.

1 Answers   Sabic,


if found error in magnetic flow meter?how can we adjust?

2 Answers   ANI Instruments, Techint,


why most of the DP transmitters using maximum range as 0-2500mmwc?why not 1000 2000 3000 4000mmwc

2 Answers   SPIC, TNPL,


What is the definition of direct acting valve & reverse acting valve

2 Answers  


What are de-saturators?

0 Answers  


Tell me the field calibration procedure step by step with diagram of pressure gauge, pressure switch, pressure transmitter, temperature switch, level switch, flow switch, flow transmitter.

0 Answers  


State bernoulli’s application.

0 Answers  


Why 1-5 vdc a standard?

1 Answers   Process Control Technologies,


what is the name of thermocople element cable from field to pannel end?

3 Answers  


why do we use 4-20 ma current why cant o-20ma

6 Answers   Southwest Cheese,


Categories
  • Civil Engineering Interview Questions Civil Engineering (5086)
  • Mechanical Engineering Interview Questions Mechanical Engineering (4456)
  • Electrical Engineering Interview Questions Electrical Engineering (16639)
  • Electronics Communications Interview Questions Electronics Communications (3918)
  • Chemical Engineering Interview Questions Chemical Engineering (1095)
  • Aeronautical Engineering Interview Questions Aeronautical Engineering (239)
  • Bio Engineering Interview Questions Bio Engineering (96)
  • Metallurgy Interview Questions Metallurgy (361)
  • Industrial Engineering Interview Questions Industrial Engineering (259)
  • Instrumentation Interview Questions Instrumentation (3014)
  • Automobile Engineering Interview Questions Automobile Engineering (332)
  • Mechatronics Engineering Interview Questions Mechatronics Engineering (97)
  • Marine Engineering Interview Questions Marine Engineering (124)
  • Power Plant Engineering Interview Questions Power Plant Engineering (172)
  • Textile Engineering Interview Questions Textile Engineering (575)
  • Production Engineering Interview Questions Production Engineering (25)
  • Satellite Systems Engineering Interview Questions Satellite Systems Engineering (106)
  • Engineering AllOther Interview Questions Engineering AllOther (1379)