how to calculate the steel for rcc slab?
plz tell me the formula for calculating the steel?
Answers were Sorted based on User's Feedback
Answer / md gulam moinuddin
there is no general formula for the calculation fo steel
(reinforcement) its depend upon the design of the structur
,for whih load and moment acting on the structure are
considered
| Is This Answer Correct ? | 611 Yes | 148 No |
Answer / mahendra gaikwad
For Tender purpose, just take valume of RCC conc.X 110 =
steel in rcc
| Is This Answer Correct ? | 529 Yes | 209 No |
Answer / shashwati nag
Ast=0.5fck/fy(1-(1-4.6Mu/fck.b.d.d))bd
| Is This Answer Correct ? | 336 Yes | 169 No |
Answer / k.srinivasa rao
for calculating the area of steel in rcc slabs,
ast = ( M ) / (.87*fy*(d-.42*xu))
where
M= moment corresponding to entire loads of span in one
meter length
fy= characteristic strength of steel
d= depth of slab
xu=lever arm depth depending upon the type of fy given
in Is:456-2000
| Is This Answer Correct ? | 216 Yes | 72 No |
Answer / aanand babasaheb chougule
Design steps of one way slab
1. Depth of slab
d= lx/20 * M.F. (M.F. = Modification factor)
Assume the dia. of bar (8, 10, 12) and
Final overall depth
D= d+15+0/2
d= d-15-0/2
2. Effective Span
This is taken as the lesser of the followings
a) Center to center distance between followings
L= lx + t
L= lx + d
3. Load
Consider 1m width of the slab and find out the total udl
a) W = (Self weight + Live Load + Floor finish)
b) Find factor load
Wu = 1.5 * w
4. Factor bending moment
Mu = Wu * l²/8
5. Equating Mu limit to Mu find the depth req. if it is
less than‘d’ than O.K otherwise
Increase D & repeat 2, 3, and 4
Mulimit = Mu
6. Area of main steel
Pt = 50fck/fy (1-√1 – 4.6 Mu / fck bd²)
Ast = Pt/100 *100* d
7. Spacing of main steel
S = Area one bar * 1000/ Ast
Check: - a) 3d
b) 450 mm
8. Distribution Steel
Astd = 0.15 % of Ag -Fe 250 (mild)
= 0.12% of Ag – Fe 415/5000 (torque)
Ag = b.D
9. Spacing of distribution steel
S= Area one bar * 1000/ Astd
Check: - a) 5d
b) 450 mm
10. Check for depth
a) Žv = V/bd
b) Pt —› Zc
c) Zv < Zc …….. No shear reinforcement req.
| Is This Answer Correct ? | 146 Yes | 35 No |
Answer / vinesh
Ast=(0.5Fck/Fy) into(1-(in sqrt(1-((4.6Mu)/Fck.bd^2))into bd
Fck=grade of cement i.e M25, M20
Fy=grade of steel i.e.Fe415,Fe250
Mu=moment
b=width
d=depth
| Is This Answer Correct ? | 140 Yes | 36 No |
Two Methods, First from Calculation, 2nd using SP16
1st Method Compute K= Mu/(fcu x b x d^2)
for Fy = 415 if K<= 0.138 Singly Reinforced
Calculate Z/d = 0.5 + sqrt { 0.25 - K/0.865}
Area of Steel = Mu / { 0.87 x fy x Z }
Z is Lever Arm Distance Between CG of Tension and Compression Force
2nd Method
Calculate Mu /{b x d^2}
Check Table 2 to 5 of SP16 based on Concrete Grade
It gives Percentage of Steel Pt for given Grade of Concrete,steel and Mu/{bxd^2}
| Is This Answer Correct ? | 111 Yes | 44 No |
Answer / dinesh chahal
it will be depend on the area. just calculate the area then
spacing.,.,after than total length/ spacing = no of bar. use
the formula d*d/162 = total steel waight per meter.,.,.
multiply total to total length= total steel in the rcc slab
| Is This Answer Correct ? | 63 Yes | 15 No |
Short formulas.
for coloums=1% t0 5% of concrte volume
for beams=.7% t0 1%
for beams=.5% .8%
| Is This Answer Correct ? | 67 Yes | 22 No |
why there is need to provide shear reinforcement?give the basic reason?
9 Answers JMC, L&T, Power Grid,
1)define the critical items in rcc framed G+18 bldg. as Cr Activity 1,Cr Activity 2,Cr Activity 3...etc. 2)on what logic is MSP and Primavera planning based.FS SF FF...
Why do we provide development length in RCC?
you are planning to paint a newly fabricated workshop building made of structural steel of 10 tons total mass.you are require to paint 1 cot of primer and 2 coats of top coat.How many liters of primer and top coat you will request
Can we use PPC cement for RCC works? Upto which grade it can be used?
Dear Sir What is the Contraction joint for base Slab
what"s the purpose of dry lean concrete(DLC)and where it"ll be use it?
a) we have 30nos., 300mm dia, 4m length double under reamed piles.calculate excavation quantity.b) tell concrete qty. also.
2. What are the grades of steel used in the concrete design?
Clay and silt content in a good brick earth must be at least
how many numbers of Precast concrete hollow blocks (400mmx200mmx200mm) can be installed by the one mason and two helper in one day.
I'm puting roof slab M20 Design Concrete,Twoway slab how many days wait for remooving of shuttering?
Civil Engineering (5086)
Mechanical Engineering (4456)
Electrical Engineering (16639)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)