how to calculate the steel for rcc slab?
plz tell me the formula for calculating the steel?
Answers were Sorted based on User's Feedback
Answer / b.narayana murthy
For estimation purpose , the quantity of steel will be 120
kgs x rcc quantity
| Is This Answer Correct ? | 17 Yes | 18 No |
Answer / muhammad
we cant calculat the steel how much we used on per sq.ft
Becos
1) it depend on structur for exam:-in G+7 we used 7kg to 8kg ,inG+4 we used 2.5kg to4kg, as in colleg,masjed,tempul we used 10 to 14kg
As one more importan it depen on the field (soiel)
It have maney resion
We the ferfet formula how we can make concret accourding to satwation on the field. But for steel desing we have work accourding to the fiel
| Is This Answer Correct ? | 6 Yes | 7 No |
Answer / amjad khan
3/8 dia of bar,one ft of weight .170kg and far and calculate of steel farmola one ft (d^2/52.83)=.170kg
| Is This Answer Correct ? | 0 Yes | 1 No |
Answer / vineeth
thumb rule 4.5kg/sqft for residential and 6kg/sqft for
commercial.
| Is This Answer Correct ? | 4 Yes | 8 No |
For 25mm thick plastering how much sand and cement is used for 1 sft
1 Answers Assurance, Design Consortium,
pointing raju,ayesha says"he is the son of my mother's brother's wife". how is ayesha related to raju?
The designs required to construct a building are ––
Machine mix is better than hand mixing to get––
i am laying a base of dimensions 6.5feet by 7feet by 1.25 feet depth how many bags of 25kg cement and how many bags of 25kg sand will i need
cement mortar1:5 12mm thick and one bags cement how much area pleastering please give anwser
12 Answers DeSigns Inc, L&T, Marg, Sand, Vee Technologies,
what are the minimum compressive strength required for the concrete cube for different grades & different days .Please give me an answer.
Are you good at detailing and explain about the project you have worked on detailing?
What is the Hardness of M-40 grade concrete, general and theoratical
1) One mason per day how many cu.m work will do as per list given a) Brick work,hollow brick work and cc block work and plastering how many m2 per day 2) one carpenter per day how many m2 will do as well as scaffolding how many m3
12 Answers Al-Futtaim, Arihant, GS, Gulf, L&T, NCC, Paras Buildtech, PR Constructions, Ramco,
how much solid block in 1m3
why we create short columns under grade slab?
Civil Engineering (5086)
Mechanical Engineering (4453)
Electrical Engineering (16638)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)