how to calculate the steel for rcc slab?
plz tell me the formula for calculating the steel?
Answer Posted / shafiullah
ast = ( M ) / (.87*fy*(d-.42*xu))
Is This Answer Correct ? | 89 Yes | 32 No |
Post New Answer View All Answers
what quantities of work done in terms of sq.mts/day/ of 8hrs for each varpenter (shuttering) and Steel fitter in terms of Tonnes. For slabs, Columns etc.?
Define What is passive earth pressure ?
asubmerged weir is one in which the water level on the down stream side of the weir is just at the crest level below the crest level above the crest level at stamp elevation as water surface on upstream
how much of the strength comes from post-production curing
how to prepare site mix design
Explain what is the difference between built area and super built up area?
For fine aggregate which is most suitable River sand or crusher sand & why ?
What is the wall thickness of NP-3&NP-4 hume pipe as per I.S code
What is the basic difference between OPC
For elevated service Reservoirs what will be the output of each skilled carpenter and bar bender.
What is difference between limit state and working stress method? How it is applies in building structure.
how much shouid be the rate for ready mix concrete per cubic meter
How u can calculate the Octagon ring distance from center of raft in 275 mtr chimney slipform errection? cantact no:0993455097
1.Why we are preferring 43 grade cement than 53 grade cement. 2. Approximate cost difference between 43 and 53 grade cement. Thanks.
how to calculate number of bitumen for road asphalt