Sir what reason the deshuttring of column 1 day after casting and slab deshuttring time 14 days after casting
Answer / rethina kumar
generally concrete is strong in compression, weak in tension, that is reason we providing reinforcement in tension zone.
1.column is compression zone, so one day is enough to deshutter
2.slab is tension zone, so it need minimum 14 days to deshutter
| Is This Answer Correct ? | 30 Yes | 0 No |
for basic costing, how can we calculate how much amount of steel and cocrete will go in per sqft? and what are the thumbrules?
How much of the strength of concrete comes from post- production curing?
0 Answers EE Limited, Focus, Lafarge,
how to calculate the steel for beams and columns for tender purpose? any formula have?
what is the % wastage of cement in rcc
which Indian standerd code is used for billing
4 Answers Desai Construction, DLF, NKG Infrastructure,
why we provide plastic sheet under lean concrete/pcc.?
1.how to calculate 4*3 runner qty in cft. 2.how to calculate the nails qty.(column,beam,slab) 3.if any formula for binding wire qty calculation.
reinforcement lapping for short pile and long pile
why red bricks & cinders used in toilet sunken filling. if coarse aggreate used wat the probelem
Define aligned dimension?
Can anybody explain with the help of sketeches that what are 2legged , four legged & 6legged stirrups and how to calculate cut length of diamond ring(stirrups)?
what is slump
5 Answers JMC Projects, Puravankara,
Civil Engineering (5086)
Mechanical Engineering (4456)
Electrical Engineering (16639)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)