how to calculate the steel for rcc slab?
plz tell me the formula for calculating the steel?
Answer Posted / engr shabbir
Short formulas.
for coloums=1% t0 5% of concrte volume
for beams=.7% t0 1%
for beams=.5% .8%
| Is This Answer Correct ? | 67 Yes | 22 No |
Post New Answer View All Answers
Explain the different types of roofing systems?
What is kn measurement?
what energized you to complete your course?
a rectangle grill of length 72 inch x 20 inch width.how to calculate bar spacing ,bar consist 8 mm thickness and spacing of bar is 2 inch.. calculate no of bar with formula
what quantities of work done in terms of sq.mts/day/ of 8hrs for each varpenter (shuttering) and Steel fitter in terms of Tonnes. For slabs, Columns etc.?
procedure for preliminary selection of size of column of 5 storey building
will fix foundation bolts at site with out template is there any procedure?
what is the productivity in aluminium shuttering per day
what are the grades of concrete?where and or what purpose a particular grade is used in a particular structure?
Wats the formula of eccentric footing and how was calculated from concrete qty
what will happen if one could not properly follow the spacing of slab reinforcement bar?
what would be the design load of R.C.C Cooling tower per cell.?
please send latest placement papers of hpcl officers trainee test. i will be very thankful to you.
We are into industrial flooring (epoxy flooring) business. We buy material from manufacturers.We supply and laying the to companies. In our billing what tax/ taxes to be claimed from companies? Are we applicable for only WCT or any else?
How to calculate sand , cement quantity for 23mm thk brick work(10x10)