Golgappa.net | Golgappa.org | BagIndia.net | BodyIndia.Com | CabIndia.net | CarsBikes.net | CarsBikes.org | CashIndia.net | ConsumerIndia.net | CookingIndia.net | DataIndia.net | DealIndia.net | EmailIndia.net | FirstTablet.com | FirstTourist.com | ForsaleIndia.net | IndiaBody.Com | IndiaCab.net | IndiaCash.net | IndiaModel.net | KidForum.net | OfficeIndia.net | PaysIndia.com | RestaurantIndia.net | RestaurantsIndia.net | SaleForum.net | SellForum.net | SoldIndia.com | StarIndia.net | TomatoCab.com | TomatoCabs.com | TownIndia.com
Interested to Buy Any Domain ? << Click Here >> for more details...


Why we do design mix of concrete when there is nominal
method using the IS-Code available ?

Answers were Sorted based on User's Feedback



Why we do design mix of concrete when there is nominal method using the IS-Code available ?..

Answer / mallikarjuna (nitw)

to ensure required |Target Mean Strength by controlling the
parameters of aggregate,sand and water accurately ....n
also to design higher grade of concrete ...

....incase of nominal mis method(say),M15 means 15mpa
comp.srength on 28 days using 1:2:4 proportions without
considering various conditions of conareting
materials ...the same will be rectified in design mix .

simply nominal mix is blind technique where as design mix
is live n vibrant method of mix design in concrete
technology to achieve anticipated TMS.

Is This Answer Correct ?    46 Yes 3 No

Why we do design mix of concrete when there is nominal method using the IS-Code available ?..

Answer / aasinghai

to achieve economy and safety

Is This Answer Correct ?    34 Yes 4 No

Why we do design mix of concrete when there is nominal method using the IS-Code available ?..

Answer / arunkumar.t

to save an optimum content of cement, from 7.5 to 8 bags of
cement to 6.6 bags of cement per CuM

Is This Answer Correct ?    28 Yes 11 No

Why we do design mix of concrete when there is nominal method using the IS-Code available ?..

Answer / sudheer

To acheive best possible concrete with the ingredients
available at particular location design mix is used.

Is This Answer Correct ?    17 Yes 1 No

Why we do design mix of concrete when there is nominal method using the IS-Code available ?..

Answer / santosh

design mix of concrete give the exact quantity of material
such as cement, sand, aggregate & water.so that economy in
the material can be possible. higher strength of concrete
can be achieved with min. content of admixtures

Is This Answer Correct ?    12 Yes 0 No

Why we do design mix of concrete when there is nominal method using the IS-Code available ?..

Answer / nagori salim

The basic difference betn the two is;

Nominal - Volumetric Batching.

Design - Weight Batching.

In design mix degree of quality & control on quantity is
highly maintained.

Is This Answer Correct ?    12 Yes 2 No

Why we do design mix of concrete when there is nominal method using the IS-Code available ?..

Answer / subhendu,jadavpur

In the code specified ratio there is no any consideration
of workebility, which in one of the mandetory aspects to be
considered. But by mix design we can design the concrete of
required workebility without sacrificing the strength.

Is This Answer Correct ?    8 Yes 1 No

Why we do design mix of concrete when there is nominal method using the IS-Code available ?..

Answer / raju mandal

Because the properties of available material is varies from
site to site.It is preferable because we want to get
strength of concrete at optimum cost.You can use nominal
method of mix if you are able to provide standard
characteristics to the all material.

Is This Answer Correct ?    7 Yes 1 No

Why we do design mix of concrete when there is nominal method using the IS-Code available ?..

Answer / sailesh kaw

Design mix is carried out for the optimization of concrete,
to increase its durabilty and to decrese its permeability.
WC ratios is also reduced.

Design mix is based on the specific weights of the material
where as 1:2:4, 1:3:6 etc are volumetric based design

Is This Answer Correct ?    7 Yes 2 No

Why we do design mix of concrete when there is nominal method using the IS-Code available ?..

Answer / rakesh kumar mallik

By design mix of concrete we can achieve more workable
concrete without hampering the strength of concrete which is
not possible in nominal mix of concrete.
By design mix we have have control over the quantity of
material,water cement ratio to achieve the required strength.

Is This Answer Correct ?    0 Yes 0 No

Post New Answer

More Civil Engineering Interview Questions

Why there is no use of sea water in producing electricity

20 Answers   Infosys,


What is demising walls?

0 Answers  


brick work 1cum kitne cft hote hai

2 Answers   Harit Dharaa,


1m3 of brick is equal to how many cft of brick

9 Answers   DG Khan Cement,


what will be the difference in compressive test results for a 150 mm cube, a 150 mm cylinder and a 300 mm cube

5 Answers  


how much quantity of cement and sand required for construction of 10 cum brick work( Brick size 3"*4"*9"(Standard size ) an d for 10 cum construction of SSM (Size stone masonary) with Cm 1:6 for both.

11 Answers   GRC, KEC, L&T, Techno Electric and Engineering, UPENN,


Difference between lateral ties and stirrups?

6 Answers  


how much shuttering oil required for 100 sqm shuttering?

1 Answers   L&T, NCC,


calculate the cost for AAC block wall of 15cum?

2 Answers  


can you please tell me what the current rate of construction material and different construction labourers charge in bangalore ???

0 Answers  


The Instrument used to determine colour of water is called A] Turbidimeter B] osmoscope C] Barometer

1 Answers  


what do u mean by shear?and tension?

6 Answers   L&T, Shoba Devlopers,


Categories
  • Civil Engineering Interview Questions Civil Engineering (5086)
  • Mechanical Engineering Interview Questions Mechanical Engineering (4456)
  • Electrical Engineering Interview Questions Electrical Engineering (16639)
  • Electronics Communications Interview Questions Electronics Communications (3918)
  • Chemical Engineering Interview Questions Chemical Engineering (1095)
  • Aeronautical Engineering Interview Questions Aeronautical Engineering (239)
  • Bio Engineering Interview Questions Bio Engineering (96)
  • Metallurgy Interview Questions Metallurgy (361)
  • Industrial Engineering Interview Questions Industrial Engineering (259)
  • Instrumentation Interview Questions Instrumentation (3014)
  • Automobile Engineering Interview Questions Automobile Engineering (332)
  • Mechatronics Engineering Interview Questions Mechatronics Engineering (97)
  • Marine Engineering Interview Questions Marine Engineering (124)
  • Power Plant Engineering Interview Questions Power Plant Engineering (172)
  • Textile Engineering Interview Questions Textile Engineering (575)
  • Production Engineering Interview Questions Production Engineering (25)
  • Satellite Systems Engineering Interview Questions Satellite Systems Engineering (106)
  • Engineering AllOther Interview Questions Engineering AllOther (1379)