1 Cum Brick Work CM 1: 6 - How Many Bricks ,sand,Cement
Required? Brick Size 9" 4.5" 3"

Answers were Sorted based on User's Feedback



1 Cum Brick Work CM 1: 6 - How Many Bricks ,sand,Cement Required? Brick Size 9" 4.5" 3&q..

Answer / hussain

Volume of 1 Brick = 0.230*0.115*0.075 = 0.002
So No of brick req for 1 m3 = (1/0.002) = 500 Nos

1.7 bag of Cement required

0.31 cum sand required for 1 cum of brickwork

Is This Answer Correct ?    717 Yes 234 No

1 Cum Brick Work CM 1: 6 - How Many Bricks ,sand,Cement Required? Brick Size 9" 4.5" 3&q..

Answer / raja j

brick size in meter=.23*.115*.075 =.0019
add 10 mm mortar for ech sides=(.24*.125*.085)=(.0025)

bricks required for 1 m3 =(1/(0.0025)=400 nos

mortar required =(.0025-.0019)*400=.24

add 15% for wastage = (.24*1.15)=.276m3

so required sand is =.276 m3

cement is =(1440/6)=240*.276= 66 kg

Is This Answer Correct ?    283 Yes 134 No

1 Cum Brick Work CM 1: 6 - How Many Bricks ,sand,Cement Required? Brick Size 9" 4.5" 3&q..

Answer / ajeet kumr bhatnagar

Actual brick size 230*115*76

So No's of bricks in 1 m3=1÷.23*.115*.076=498nos
Now consider 10mm thick mortar
Now bricks size =240*125*86cm
No's of bricks in 1m3=1/.24*.125*.86=388nos
5% wastge=388+20=418nos actual
Mortar 498-388=110nos bricks
=110*.23*.115*.076=.22m3
30% for dry volume=0.286m3
Wastage 5%=0.015
Net volume=.286+.015=.3(approx)
Cement=.3÷7=0.042=.042÷.0345=1.24 bags

Sand=.042*6=.252m3 or.252*35.28=8.89cft

Is This Answer Correct ?    161 Yes 30 No

1 Cum Brick Work CM 1: 6 - How Many Bricks ,sand,Cement Required? Brick Size 9" 4.5" 3&q..

Answer / tipu sultan

standard size of brick
=(.19×.09×.09)m

volume of brick
=(.19×.09×.09)m^3
=0.001539
=0.00154m^3

with mortar brick size
=(.20×.10×.10)m
& volume=
=(.20×.10×.10)m^3
=0.002m^3

for volume 0.002m^3 then no. of brick=1

so that
for 1m^3 then nos. of brick = 1÷.002 = 500nos.

Is This Answer Correct ?    136 Yes 18 No

1 Cum Brick Work CM 1: 6 - How Many Bricks ,sand,Cement Required? Brick Size 9" 4.5" 3&q..

Answer / ajeet kumar bhatnagar

consider brick joint 10mm.
Brick volume 0.23x0.115x0.76=.0020m3
So for 1m3 brick work brick required=1/.0020=500nos
Now taking joint ,volume =.240x.125x0.086=.00245
Now for 1m3 brick work brick require=1/.00258= 388nos
So mortar volume =500-388=112nos brick=112x0.0020=0.32m3
For 1:6 mortar Cement 1/7x0.320=0.0457m3=0.00457/0.0345=1.32bags=1.32x50=66 kg
Sand=6/7x0.32=.274m3x35.28=9.67cft

Is This Answer Correct ?    67 Yes 14 No

1 Cum Brick Work CM 1: 6 - How Many Bricks ,sand,Cement Required? Brick Size 9" 4.5" 3&q..

Answer / md.furqan anasri

Bricks :395
Cement:1.25 Bags (CPWD)
C-sand:10 cft

Is This Answer Correct ?    88 Yes 42 No

1 Cum Brick Work CM 1: 6 - How Many Bricks ,sand,Cement Required? Brick Size 9" 4.5" 3&q..

Answer / guest

500 bricks,

Is This Answer Correct ?    52 Yes 31 No

1 Cum Brick Work CM 1: 6 - How Many Bricks ,sand,Cement Required? Brick Size 9" 4.5" 3&q..

Answer / b.jagan

Per 1m3 B.W required materials
Brick=500mom's
Cement=75kg
Sand=10.5cft

Is This Answer Correct ?    32 Yes 14 No

1 Cum Brick Work CM 1: 6 - How Many Bricks ,sand,Cement Required? Brick Size 9" 4.5" 3&q..

Answer / asmar ahmed

cement = 1.40 Bags
sand = 10.50 Cft
Bricks = 466 Nos

Is This Answer Correct ?    33 Yes 20 No

1 Cum Brick Work CM 1: 6 - How Many Bricks ,sand,Cement Required? Brick Size 9" 4.5" 3&q..

Answer / saeed khan

Brick=500
Sand=.257
Cement=1.225 bags

Is This Answer Correct ?    14 Yes 7 No

Post New Answer

More Civil Engineering Interview Questions

# 1. Water observation capacity (MAximum)of Solid bricks # 2. Minimum Crushing Strength of Solid Blocks.

4 Answers   Brigade,


What is diversion tunnel in a dam?

0 Answers  


Why there is no use of sea water in producing electricity

20 Answers   Infosys,


why hanger rods are used in beam

3 Answers  


how to Concrete cubes testing curing time 7 days casting date 24.05.17 testing date ?

0 Answers  






Why Should Curing Not Be Done By Ponding And Polythene Sheets?

0 Answers   Bechtel,


what is formula to calculate compressive strength of concrete or procedure??

4 Answers  


What is semirigid connections?

0 Answers  


m30 mix proportion as per IS code

4 Answers  


Requirement of cement, and steel 1:2:4 ratio concrete in 1128 Sqft area(Cement No of bags, steel in Kgs)

0 Answers  


what is the cost of per cum of pile foundation?

1 Answers  


what is the most suitable foundation when construct a bird watching tower in a marshy land

0 Answers  


Categories
  • Civil Engineering Interview Questions Civil Engineering (5085)
  • Mechanical Engineering Interview Questions Mechanical Engineering (4451)
  • Electrical Engineering Interview Questions Electrical Engineering (16632)
  • Electronics Communications Interview Questions Electronics Communications (3918)
  • Chemical Engineering Interview Questions Chemical Engineering (1095)
  • Aeronautical Engineering Interview Questions Aeronautical Engineering (239)
  • Bio Engineering Interview Questions Bio Engineering (96)
  • Metallurgy Interview Questions Metallurgy (361)
  • Industrial Engineering Interview Questions Industrial Engineering (259)
  • Instrumentation Interview Questions Instrumentation (3014)
  • Automobile Engineering Interview Questions Automobile Engineering (332)
  • Mechatronics Engineering Interview Questions Mechatronics Engineering (97)
  • Marine Engineering Interview Questions Marine Engineering (124)
  • Power Plant Engineering Interview Questions Power Plant Engineering (172)
  • Textile Engineering Interview Questions Textile Engineering (575)
  • Production Engineering Interview Questions Production Engineering (25)
  • Satellite Systems Engineering Interview Questions Satellite Systems Engineering (106)
  • Engineering AllOther Interview Questions Engineering AllOther (1379)