1 Cum Brick Work CM 1: 6 - How Many Bricks ,sand,Cement
Required? Brick Size 9" 4.5" 3"
Answers were Sorted based on User's Feedback
Answer / hussain
Volume of 1 Brick = 0.230*0.115*0.075 = 0.002
So No of brick req for 1 m3 = (1/0.002) = 500 Nos
1.7 bag of Cement required
0.31 cum sand required for 1 cum of brickwork
| Is This Answer Correct ? | 717 Yes | 234 No |
Answer / raja j
brick size in meter=.23*.115*.075 =.0019
add 10 mm mortar for ech sides=(.24*.125*.085)=(.0025)
bricks required for 1 m3 =(1/(0.0025)=400 nos
mortar required =(.0025-.0019)*400=.24
add 15% for wastage = (.24*1.15)=.276m3
so required sand is =.276 m3
cement is =(1440/6)=240*.276= 66 kg
| Is This Answer Correct ? | 283 Yes | 135 No |
Answer / ajeet kumr bhatnagar
Actual brick size 230*115*76
So No's of bricks in 1 m3=1÷.23*.115*.076=498nos
Now consider 10mm thick mortar
Now bricks size =240*125*86cm
No's of bricks in 1m3=1/.24*.125*.86=388nos
5% wastge=388+20=418nos actual
Mortar 498-388=110nos bricks
=110*.23*.115*.076=.22m3
30% for dry volume=0.286m3
Wastage 5%=0.015
Net volume=.286+.015=.3(approx)
Cement=.3÷7=0.042=.042÷.0345=1.24 bags
Sand=.042*6=.252m3 or.252*35.28=8.89cft
| Is This Answer Correct ? | 161 Yes | 30 No |
Answer / tipu sultan
standard size of brick
=(.19×.09×.09)m
volume of brick
=(.19×.09×.09)m^3
=0.001539
=0.00154m^3
with mortar brick size
=(.20×.10×.10)m
& volume=
=(.20×.10×.10)m^3
=0.002m^3
for volume 0.002m^3 then no. of brick=1
so that
for 1m^3 then nos. of brick = 1÷.002 = 500nos.
| Is This Answer Correct ? | 136 Yes | 18 No |
Answer / ajeet kumar bhatnagar
consider brick joint 10mm.
Brick volume 0.23x0.115x0.76=.0020m3
So for 1m3 brick work brick required=1/.0020=500nos
Now taking joint ,volume =.240x.125x0.086=.00245
Now for 1m3 brick work brick require=1/.00258= 388nos
So mortar volume =500-388=112nos brick=112x0.0020=0.32m3
For 1:6 mortar Cement 1/7x0.320=0.0457m3=0.00457/0.0345=1.32bags=1.32x50=66 kg
Sand=6/7x0.32=.274m3x35.28=9.67cft
| Is This Answer Correct ? | 67 Yes | 14 No |
Answer / md.furqan anasri
Bricks :395
Cement:1.25 Bags (CPWD)
C-sand:10 cft
| Is This Answer Correct ? | 88 Yes | 42 No |
Answer / b.jagan
Per 1m3 B.W required materials
Brick=500mom's
Cement=75kg
Sand=10.5cft
| Is This Answer Correct ? | 32 Yes | 14 No |
Answer / asmar ahmed
cement = 1.40 Bags
sand = 10.50 Cft
Bricks = 466 Nos
| Is This Answer Correct ? | 33 Yes | 20 No |
How we can calaculate materials required for block work(1m3) block size 33cm x 20 cm x 17 cm, mortar 1:6
can u use instead of water milk for concreting
What is portland cement
which has high compressive strength between hollow block and brick masonry?
How to find CN by using arcgis 9.3?
all engineering filed in which branch mother branch
22 Answers L&T, Manoj Pharma Ltd,
how much steel provide in 1m cube r.c.c
Can anybody help me by attaching files , formats for quality checks of common building materials like cement , concrete , bricks , sand and aggregates? Regards,
45 Answers CDS, L&T,
for rcc which condition will u adopt now
how to calculate the steel quantity for columns and beams
what is the grade of concrete?
Please tell me Detail cost of providing& laying nominal mix design 1:2.5:5,40mm nominal size.curing complete e/c cost of form work in foundation and plinth i/c carriage.
Civil Engineering (5086)
Mechanical Engineering (4456)
Electrical Engineering (16639)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)