1 Cum Brick Work CM 1: 6 - How Many Bricks ,sand,Cement
Required? Brick Size 9" 4.5" 3"
Answer Posted / md.furqan anasri
Bricks :395
Cement:1.25 Bags (CPWD)
C-sand:10 cft
| Is This Answer Correct ? | 88 Yes | 42 No |
Post New Answer View All Answers
What is chemical composion test
Which is the latest version of solidsworks?
How to make tiles floor step by step procedure?
qty. of cement & sand required (100sq.mtr) for fixing of floor and wall tiles also fixing of marble stone on the floor
calculate the quantity of water for 1:6 cement mortar
If we are providing concrete joint in every 10m with water stopper in water tank wall then is it necessary to cut the steel at joint section?
What is the difference between EPC,DBOOT and BOOT.
Design a cantilever slab to carry a live load of 2000 N/m2. The overhang of the slab is 1.20m. b) A slab over a room is 4.75m x 4.75m. The edges of the slab are simply supported and the corners are not held down. The live load an the slab is 300 Kg/m2. The slab has a bearing of 15cm. On the supporting walls. Design the slab as per Rankine - Grashoff theory. Assume weight of R.C.C. = 2400 Kg/m2.
what is yield and tensile strength of steel, if steel has yeilding strength of 60 psi than how much its tensile strength?
Which prize is the alternative to the NOVEL Prize?
I need old MMUP exam question and answer for Civil engineering
how to calculate the density for high density concrete ? or is it same as the density of RC?
How do you measure water flowing through 300mm diameter pipes?
what is the water-cement ratio of mix design while 30mpa in 7 days?
Slab quantity