How to calculate the cement, sand quantity for plastering?
(10'x10')10mm thick ratio 1:5. wht"s the formula?
Answers were Sorted based on User's Feedback
Answer / bala ganesh
TOTAL QUANTITY OF PLASTERING=3.05*3.05*.01=.093 cu.m
by thumb rule
.75 cu.m of plastering requires =350kg of cement
1750 kg of sand for
the ratio of 1:5 (the weights are calculated with specific
gravities) from this
add 30% extra for wastage and uneveness=.121 cu.m
so for .121 cu.m of plaster requires = 56.5 kg of cement
282.5 kg of sand
Is This Answer Correct ? | 16 Yes | 11 No |
Answer / rustam sahu
Suppose we have a room size of 10 ft. x 10 ft. where height of room is 11 feets and width of plastering is 1/2 inch.
1/2 inch = 1/2 divided by 12 = 0.04167 feet
now, let us find out the wet volume for plastering just for one side of wall..
i.e., (length x width x height ) =
= 10 x 0.04167 x 11
= 4.583 c.ft.
for dry volume, segregation value 1.52
Dry volume = wet vol. x seg. value
= 4.583 x 1.52
= 6.97 c.ft.
also, plastering ratio (1:6) sum of ratio = 1+6= 7
per quantity = dry vol. divided by sum of ratio
i.e., = 6.97 / 7 = 0.9957
note: 1 bag cement carries 1.25 c.ft
for cement per bag = 0.9957 /1.25 = 0.7965 bag (for 1 wall)
since a room have 4 walls. so,
0.7965 x 4 = 3.1862 bag
add 10% extra for irregularities at joints or corners
i.e., 3.186 + 0.3186 = 3.5 bags
for sand = per quantity x per ratios x no. of walls
= 0.9957 x 6 x 4
= 23.8968 c.ft
Answer = a room size (10 x 10) ft. having 11 feets height and 1/2 inch width of plastering will required 3.50 bag of cement and 23.89 c.ft. of sand
Is This Answer Correct ? | 4 Yes | 0 No |
Answer / sunandan sharma
10feet = 10/3.28=3.048m
volume = 3.048x3.048x.01=.093 cubic meter
for dry material factor is 1.2
so quantity of dry material=0.093x1.2= 0.11cum
now the ratio is (1:5)
so cement=0.11/6 =0.018cum=0.64(.018x28.8bags)
=0.518bags=25.92kg
sand=0.018x5=0.09cum=3.17cuft
Is This Answer Correct ? | 4 Yes | 2 No |
Answer / amir shahzad
plaster area =100
thikh of plaster=10mm
plaster voleem=1/2x1/12x1oo=1.5
dry metreal one cft = 4.166
1.5x4.166=6.249
ratio 1:4=5
fromula = 6.249x1/5=1.25/1.24=0.99 cement bage
6.249x4/5=4.99 send
Is This Answer Correct ? | 5 Yes | 3 No |
Answer / anant dawale
For 100 sqft;(9.295 m2)Plastering
3.0488m x3.0488m ;Thickness=0.02m (20mm)
Dry volume of mortar= 3.048 x 3.048 x.02= 0.1859 m3
Wet volume of mortar (30%) = 0.1859 x 1.3= 0.2416 m3
Mortar Proportion =1:5.
Volume of Cement= Wet volume /(1+5)i.e .02416/6=0.0403 m3
Qty of Sand=0.0403 X 5 = 0.201 m3.
Volume Of Cement/Bag= 0.034 m3
i.e.for 1 Bag of Cement ; Sand = 0.17 m3
Is This Answer Correct ? | 5 Yes | 3 No |
Answer / aravinth
Cement mortar 1:2 - 1m3
How much of cement
How much of sand
How much of water
Is This Answer Correct ? | 2 Yes | 0 No |
Answer / harish po
100sqm,12mm thick,CM 1:4 plastering
volume = 100x(12/1000)=1.20 cum
Add 30% as bulking of sand=(1.2x30)/100=0.360 cum
Add 20% as wastage =((1.2+0.36)x20)/100=0.312 cum
Total=1.872 cum
volume of mortar=1.872/(1+4) =0.374 cum
volume of cement = 0.374 cum x 30 bag/cum =10.77 bag
10.77 bag x 50 kg/bag =538.5 kg for 100 sqm
(for 1sqm 12mm thick,CM 1:4 cement required=5.385kg)
volume of sand = 0.374 x 4 (CM 1:4) =1.496 cum for 100 sqm
(for 1sqm 12mm thick,CM 1:4 sand required=0.01496 cum/0.53cft)
Is This Answer Correct ? | 3 Yes | 1 No |
Answer / ashok
If we Consider 12 mm thick plaster(1:6)
Area for Calculation=1M x 1M = 1 Sqm
Quantity in Cum.=1M x 1M x 0.012M = 0.012 Cum.
Proportion of Cement = [1/7=0.143 x 0.012=0.002 Cum/0.035 x 50 = 2.45 K.g
Add 25%+5% [Dry volumn + Wastage] =[ 2.45 x 30% = 3.18 K.g]
Proportion of Send = [6/7=0.857 x 0.012=0.010 Cum x 35.32 = 0.363 cft
Add 25%+5% [Dry volumn + Wastage] =[ 0.363 x 30% = 0.472 cft]
Is This Answer Correct ? | 1 Yes | 0 No |
Answer / ashok sharma
If we Consider 12 mm thick plaster(1:6)
Area for Calculation=1M x 1M = 1 Sqm
Quantity in Cum.=1M x 1M x 0.012M = 0.012 Cum.
Proportion of Cement = [1/7=0.143 x 0.012=0.002 Cum/0.035 x 50 = 2.45 K.g
Add 25%+5% [Dry volumn + Wastage] =[ 2.45 x 30% = 3.18 K.g]
Proportion of Send = [6/7=0.857 x 0.012=0.010 Cum x 35.32 = 0.363 cft
Add 25%+5% [Dry volumn + Wastage] =[ 0.363 x 30% = 0.472 cft]
Is This Answer Correct ? | 1 Yes | 0 No |
how much quantity of tile placing can be finished by one mason per day?
How to build the floor to ceiling bookcase?
what is called camber in the road ?
how to calculate required shuttering material like props,spans,plates ..etc for a slab?
1 Answers NCC, Shoba Devlopers,
What are segregation and bleeding?
I am a civil engineer . I am also selected for sbi clerk interview which is to be held on 4th May2010 is there anybody resembling the same? what question can be asked and what should be the probable answers?
What is bending moment
how to calculate the weight of concrete
how do you calculate the quantity of steel,cement for plinth beam. (example size 41'*0.58'*1.08')
If we know the N - Value of soil and required bearing capacity how do we know what diameter and length of pile to be casted? How can we check whether the dia. and lenght of pile we have selected are most economical onse?
How did the romans get water up hills using aqua ducts?
How much ratio of water in use of 1m.cube r.c.c the ratio is (1:2:4)