How to calculate the cement, sand quantity for plastering?
(10'x10')10mm thick ratio 1:5. wht"s the formula?
Answers were Sorted based on User's Feedback
Answer / bala ganesh
TOTAL QUANTITY OF PLASTERING=3.05*3.05*.01=.093 cu.m
by thumb rule
.75 cu.m of plastering requires =350kg of cement
1750 kg of sand for
the ratio of 1:5 (the weights are calculated with specific
gravities) from this
add 30% extra for wastage and uneveness=.121 cu.m
so for .121 cu.m of plaster requires = 56.5 kg of cement
282.5 kg of sand
| Is This Answer Correct ? | 16 Yes | 11 No |
Answer / rustam sahu
Suppose we have a room size of 10 ft. x 10 ft. where height of room is 11 feets and width of plastering is 1/2 inch.
1/2 inch = 1/2 divided by 12 = 0.04167 feet
now, let us find out the wet volume for plastering just for one side of wall..
i.e., (length x width x height ) =
= 10 x 0.04167 x 11
= 4.583 c.ft.
for dry volume, segregation value 1.52
Dry volume = wet vol. x seg. value
= 4.583 x 1.52
= 6.97 c.ft.
also, plastering ratio (1:6) sum of ratio = 1+6= 7
per quantity = dry vol. divided by sum of ratio
i.e., = 6.97 / 7 = 0.9957
note: 1 bag cement carries 1.25 c.ft
for cement per bag = 0.9957 /1.25 = 0.7965 bag (for 1 wall)
since a room have 4 walls. so,
0.7965 x 4 = 3.1862 bag
add 10% extra for irregularities at joints or corners
i.e., 3.186 + 0.3186 = 3.5 bags
for sand = per quantity x per ratios x no. of walls
= 0.9957 x 6 x 4
= 23.8968 c.ft
Answer = a room size (10 x 10) ft. having 11 feets height and 1/2 inch width of plastering will required 3.50 bag of cement and 23.89 c.ft. of sand
| Is This Answer Correct ? | 4 Yes | 0 No |
Answer / sunandan sharma
10feet = 10/3.28=3.048m
volume = 3.048x3.048x.01=.093 cubic meter
for dry material factor is 1.2
so quantity of dry material=0.093x1.2= 0.11cum
now the ratio is (1:5)
so cement=0.11/6 =0.018cum=0.64(.018x28.8bags)
=0.518bags=25.92kg
sand=0.018x5=0.09cum=3.17cuft
| Is This Answer Correct ? | 4 Yes | 2 No |
Answer / amir shahzad
plaster area =100
thikh of plaster=10mm
plaster voleem=1/2x1/12x1oo=1.5
dry metreal one cft = 4.166
1.5x4.166=6.249
ratio 1:4=5
fromula = 6.249x1/5=1.25/1.24=0.99 cement bage
6.249x4/5=4.99 send
| Is This Answer Correct ? | 5 Yes | 3 No |
Answer / anant dawale
For 100 sqft;(9.295 m2)Plastering
3.0488m x3.0488m ;Thickness=0.02m (20mm)
Dry volume of mortar= 3.048 x 3.048 x.02= 0.1859 m3
Wet volume of mortar (30%) = 0.1859 x 1.3= 0.2416 m3
Mortar Proportion =1:5.
Volume of Cement= Wet volume /(1+5)i.e .02416/6=0.0403 m3
Qty of Sand=0.0403 X 5 = 0.201 m3.
Volume Of Cement/Bag= 0.034 m3
i.e.for 1 Bag of Cement ; Sand = 0.17 m3
| Is This Answer Correct ? | 5 Yes | 3 No |
Answer / aravinth
Cement mortar 1:2 - 1m3
How much of cement
How much of sand
How much of water
| Is This Answer Correct ? | 2 Yes | 0 No |
Answer / harish po
100sqm,12mm thick,CM 1:4 plastering
volume = 100x(12/1000)=1.20 cum
Add 30% as bulking of sand=(1.2x30)/100=0.360 cum
Add 20% as wastage =((1.2+0.36)x20)/100=0.312 cum
Total=1.872 cum
volume of mortar=1.872/(1+4) =0.374 cum
volume of cement = 0.374 cum x 30 bag/cum =10.77 bag
10.77 bag x 50 kg/bag =538.5 kg for 100 sqm
(for 1sqm 12mm thick,CM 1:4 cement required=5.385kg)
volume of sand = 0.374 x 4 (CM 1:4) =1.496 cum for 100 sqm
(for 1sqm 12mm thick,CM 1:4 sand required=0.01496 cum/0.53cft)
| Is This Answer Correct ? | 3 Yes | 1 No |
Answer / ashok
If we Consider 12 mm thick plaster(1:6)
Area for Calculation=1M x 1M = 1 Sqm
Quantity in Cum.=1M x 1M x 0.012M = 0.012 Cum.
Proportion of Cement = [1/7=0.143 x 0.012=0.002 Cum/0.035 x 50 = 2.45 K.g
Add 25%+5% [Dry volumn + Wastage] =[ 2.45 x 30% = 3.18 K.g]
Proportion of Send = [6/7=0.857 x 0.012=0.010 Cum x 35.32 = 0.363 cft
Add 25%+5% [Dry volumn + Wastage] =[ 0.363 x 30% = 0.472 cft]
| Is This Answer Correct ? | 1 Yes | 0 No |
Answer / ashok sharma
If we Consider 12 mm thick plaster(1:6)
Area for Calculation=1M x 1M = 1 Sqm
Quantity in Cum.=1M x 1M x 0.012M = 0.012 Cum.
Proportion of Cement = [1/7=0.143 x 0.012=0.002 Cum/0.035 x 50 = 2.45 K.g
Add 25%+5% [Dry volumn + Wastage] =[ 2.45 x 30% = 3.18 K.g]
Proportion of Send = [6/7=0.857 x 0.012=0.010 Cum x 35.32 = 0.363 cft
Add 25%+5% [Dry volumn + Wastage] =[ 0.363 x 30% = 0.472 cft]
| Is This Answer Correct ? | 1 Yes | 0 No |
what is the nomimanal size' os agg.'for reinforced concrete 2 th ph value of water to be used in conc. Shall generly be
what is the difference between 2 legged to 4 legged stirrups?
1 cum brick work CM1:6 how many bricks sand cement required brick size 8"4"3"
Mention different types of roof systems?
400 ku d/c clearess ketan hota hai?
how much cement and sand required for 1cum rr masonry
a simple instrument used for the measurement of colour in water is called
how many spacers we need for 1 ton reinforcement? aprox.
What is the development length given in pile?
in a corner footing of a building, column lies in one corner. in this condition i want to know if the reactive pressure of soil will be uniformly distributed throughout the footing or will be uniformly varying as in the case of eccentrical loading.
what quantities of work done in terms of sq.mts/day/ of 8hrs for each varpenter (shuttering) and Steel fitter in terms of Tonnes. For slabs, Columns etc.?
how new RCC roof joined with existing RCc roof
Civil Engineering (5086)
Mechanical Engineering (4456)
Electrical Engineering (16639)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)