how new RCC roof joined with existing RCc roof
Answers were Sorted based on User's Feedback
Answer / v.kannan
while joining of new roof slab to existing one you should
ensure whether existing roof having reinforcement projection
for joining or not to new reinforcement. if not you want to
remove the concrete up to 150-300 mm from the edge and clean
the surfaces and existing bar then connect the new one and
we can make the concrete through proper form work. and the
grade of the concrete should not less than M25
| Is This Answer Correct ? | 29 Yes | 7 No |
Answer / anup sharma
Old roof nd new roof are joined using hilty.
Hilty is the process in which a hole is made in the older
roof by drilling and hilty chemical is inserted inside the
holes and finally new reinforcement is inserted inside these
holes such that the older and the newer reinforcement stay
connected. after that form work is done and the new roof is
casted.
| Is This Answer Correct ? | 10 Yes | 2 No |
Answer / mahendra mohan srivastava, acc
sorry my dear friends we could not joint New RCC to OLd
RCC, because cement and cement concrete has a property of
srink. but we can take care of that we can taper old joint
and then new rcc will cast.
| Is This Answer Correct ? | 1 Yes | 7 No |
please send the model qn paper of jindal steel power in civil engineering..
Why the height of the bridges over the river are very low?
how to calculate the steel quantity for beams & columns also footing net? what is the formulae for calculate the steel quantity? what is mean by (100.3)plinth level?what is mean by 100.3? explained it?
Column is a compression member then why we provide reinforcement on column?
1 Answers Simplex, Thermax, Vihaan Group,
in staad which are the point is to be checked for not fail of structure
For 100 bag cement how i will calculate sand and metal aggregate.Mixing proportion 1:1.49:2.38
is there any thumb rule for calculating construction cost of the building with pile foundation per sft. area?
function of stirrup in rcc beam & column?
2 Answers KMDA-Kolkata Metropolitan Development Authority, TK Group,
On what basis we decide the formation level of the road? other then that of 50% Cutting and 50% Filling??
how to absorb to site basic corrections? which are the important correction?
Anyone have sample questions for bhel interview.please send me as Iam appearing for the interview on 19th sep2008. Kindly send this to my e-mail: arun_prasath_n@yahoo.co.in
among fine,coarse sand which is used for plaster, brickwork and RCC & why?
Civil Engineering (5086)
Mechanical Engineering (4453)
Electrical Engineering (16638)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)