How to calculate the cement, sand quantity for plastering?
(10'x10')10mm thick ratio 1:5. wht"s the formula?
Answer Posted / sunandan sharma
10feet = 10/3.28=3.048m
volume = 3.048x3.048x.01=.093 cubic meter
for dry material factor is 1.2
so quantity of dry material=0.093x1.2= 0.11cum
now the ratio is (1:5)
so cement=0.11/6 =0.018cum=0.64(.018x28.8bags)
=0.518bags=25.92kg
sand=0.018x5=0.09cum=3.17cuft
| Is This Answer Correct ? | 4 Yes | 2 No |
Post New Answer View All Answers
Special thing in designing a overhead reservoir ? which is different from an ordinary design
What are the advantages of building a dam on the river nile?
Rate analysis for construction of a solid block masonary of size 400x200x200 in C.M.1:5 in superstructure .Compressive strength 5.00 N/Sq.mm Confirming to IS: 12894:1990, with necessary scaffolding, raking of joints and pointing the same. I require rate per Cum.
what are the duties of Site Engineer in work site?
Describe Briefly The Various Methods Of Concrete Curing?
Define Who designed the city of Washington DC?
how to calclate the SHUTTERING TAKEN CONCRETE LOAD? WHAT IS THE LOAD BEARING CAPACITY IN STEEL SHUTTERING PLATE? WHAT IS THE CONCRETE LOAD IN (MASS) IN THE SHUTTERING PLATE. PLATE SIZE IS 120CM* 90CM CONCRETE WALL LENGTH IS 10M ,WIDE IS 60CM, HEIGHT IS 1.2M PLS TO SENT THE CALCULATION.
can you please tell me what the current rate of construction material and different construction labourers charge in bangalore ???
One plate (women civil worker lifting Plate - Satti) sand measures how many cubic feet?
List out some of the common problems that architect have to tackle it?
what does the grad of cement shows (denotes)?
what could be the production cost of 1 cum of concrete by CP30 plant
Define aligned dimension?
List out the potential risk factors for workers on the construction site?
How to calculate Acctually Brickwork Quantity in Honey Comb Brick in circular Soak Pit