For 100 sqft;(9.295 m2)Plastering
3.0488m x3.0488m ;Thickness=0.02m (20mm)
Dry volume of mortar= 3.048 x 3.048 x.02= 0.1859 m3
Wet volume of mortar (30%) = 0.1859 x 1.3= 0.2416 m3
Mortar Proportion =1:5.
Volume of Cement= Wet volume /(1+5)i.e .02416/6=0.0403 m3
Qty of Sand=0.0403 X 5 = 0.201 m3.
Volume Of Cement/Bag= 0.034 m3
i.e.for 1 Bag of Cement ; Sand = 0.17 m3
| Is This Answer Correct ? | 5 Yes | 3 No |
Post New Answer View All Answers
Please tell me Detail cost of providing& laying nominal mix design 1:2.5:5,40mm nominal size.curing complete e/c cost of form work in foundation and plinth i/c carriage.
Explain what is change order request?
explain the rale of the government in the construction industry
How Can I know the wastages(%) of each work added in estimating the quantity of construction materials?(Eg. Ceiling Work, Brick Work,etc....)
) Design a gussetted base for a column section consisting of one sc 250 with two cover plates 300 x 25 mm carrying an axial load of 2500 KN. The S.B.C. of soil is 250 KN/m2 and the permissible bearing pressure on concrete is 4000 KN.
what are the Task work of different labour.?
What Is the Thumb rule to calculate depth and dia of pile required to carry specified load on differeent soil
How to do bbs in excel format
how much cement and sand consuptin in 4 inch siporex walls 100 sq ft
which software is better for design and analysis of buildings (stadd pro ) or (Etabs)
what is mean by reestimation?
WHAT IS THE % OF CONCRETE WASTAGES PERMITED IN A LARGE PROJECT ? AND WHICH IS CODE TO BE REFERED.
i need the syllabus for the direcr recruitement of executive engineers in andhrapradesh
Which code is used for tor & tmt steel bar?
Why should you consider yourself fit to be hired by jindal steel.