Golgappa.net | Golgappa.org | BagIndia.net | BodyIndia.Com | CabIndia.net | CarsBikes.net | CarsBikes.org | CashIndia.net | ConsumerIndia.net | CookingIndia.net | DataIndia.net | DealIndia.net | EmailIndia.net | FirstTablet.com | FirstTourist.com | ForsaleIndia.net | IndiaBody.Com | IndiaCab.net | IndiaCash.net | IndiaModel.net | KidForum.net | OfficeIndia.net | PaysIndia.com | RestaurantIndia.net | RestaurantsIndia.net | SaleForum.net | SellForum.net | SoldIndia.com | StarIndia.net | TomatoCab.com | TomatoCabs.com | TownIndia.com
Interested to Buy Any Domain ? << Click Here >> for more details...


I'm puting roof slab M20 Design Concrete,Twoway slab how
many days wait for remooving of shuttering?

Answers were Sorted based on User's Feedback



I'm puting roof slab M20 Design Concrete,Twoway slab how many days wait for remooving of shut..

Answer / sobhanbabu

it depends upon length and width of the slab.maximum is 28
days.

Is This Answer Correct ?    1 Yes 0 No

I'm puting roof slab M20 Design Concrete,Twoway slab how many days wait for remooving of shut..

Answer / vinod

as per curing period will b 7days r 28 days the same can be
used for de shuttering

Is This Answer Correct ?    4 Yes 4 No

I'm puting roof slab M20 Design Concrete,Twoway slab how many days wait for remooving of shut..

Answer / veeramani amanthan

hi friends thank you your reply to me but now confushing
wich one i take 14 days or 28days please conform

Is This Answer Correct ?    2 Yes 3 No

I'm puting roof slab M20 Design Concrete,Twoway slab how many days wait for remooving of shut..

Answer / osbert (civ eng. student maker

hi, you dont need to wait until concrete has finally set
which is at 28days, for grade 25 of concrete at 14 days it
will have obtained strength of 16.5N/mm2 when curing is done
well. still you dont need all that strength before removing
formworks, depending on the type of cement say for quick
hardening cement even 24 hours are enough, portland
pozzolana cement about 48-72 hours you can start removing
your formworks in case you need them for other purposes.
Note, the longer they stay the better, because when you
remove them early using rough methods you may slightly
destroy soft parts.

Is This Answer Correct ?    2 Yes 3 No

I'm puting roof slab M20 Design Concrete,Twoway slab how many days wait for remooving of shut..

Answer / leo

remove the shuttering of beam shall be after 28 days

Is This Answer Correct ?    4 Yes 9 No

I'm puting roof slab M20 Design Concrete,Twoway slab how many days wait for remooving of shut..

Answer / maheswaran

After 7 days

Is This Answer Correct ?    3 Yes 11 No

Post New Answer

More Civil Engineering Interview Questions

How many types bend used in civil reinforcing

1 Answers   HARIOM TMT,


How to calculate the shuttering materials i.e MS sheet,Props,Acrow Spans,2'x3' Runner,4'x3' Runner & beam plywood bottom, sides in thumb rules in slab area

1 Answers   TATA,


what is the diferance np3 and np4 pipe

1 Answers   Sharda Construction,


define quantity of each ingredient in 1:3:6 mix concrete by volume?

0 Answers   NJS, Pratibha Industries,


What is Leastcount of 1. Total station 2. Theodolite 3. Dumpy level 4. Plane Table

3 Answers  


what is rigid pavement

3 Answers  


Name four load bearing elements (structural elements) in a framed building

1 Answers  


Are you good at detailing and explain about the project you have worked on detailing?

1 Answers  


What is bending movement formula define

1 Answers   L&T,


How much cum. Brick work can do by 1 madon

0 Answers   DLF,


how much binding wire is reqd for 1 MT

8 Answers   IVRCL,


How much cement is require in one sqft area in a G+3 residential construction.

0 Answers  


Categories
  • Civil Engineering Interview Questions Civil Engineering (5086)
  • Mechanical Engineering Interview Questions Mechanical Engineering (4456)
  • Electrical Engineering Interview Questions Electrical Engineering (16639)
  • Electronics Communications Interview Questions Electronics Communications (3918)
  • Chemical Engineering Interview Questions Chemical Engineering (1095)
  • Aeronautical Engineering Interview Questions Aeronautical Engineering (239)
  • Bio Engineering Interview Questions Bio Engineering (96)
  • Metallurgy Interview Questions Metallurgy (361)
  • Industrial Engineering Interview Questions Industrial Engineering (259)
  • Instrumentation Interview Questions Instrumentation (3014)
  • Automobile Engineering Interview Questions Automobile Engineering (332)
  • Mechatronics Engineering Interview Questions Mechatronics Engineering (97)
  • Marine Engineering Interview Questions Marine Engineering (124)
  • Power Plant Engineering Interview Questions Power Plant Engineering (172)
  • Textile Engineering Interview Questions Textile Engineering (575)
  • Production Engineering Interview Questions Production Engineering (25)
  • Satellite Systems Engineering Interview Questions Satellite Systems Engineering (106)
  • Engineering AllOther Interview Questions Engineering AllOther (1379)