how many binding wire can be required for 1 metric tonne
steel?
Answers were Sorted based on User's Feedback
Answer / s s grewal
Approximate 5.0 to 6.0 kgs binding wire is required for binding of 1.0 M.T. steel.
| Is This Answer Correct ? | 43 Yes | 9 No |
Answer / faisal
It is approximately 8 kg of Binding Wire required to bind
one Metric Ton of Steel...
| Is This Answer Correct ? | 22 Yes | 5 No |
Answer / mohammed aijaz hussain
4 kg to 5 kg of 16 guage binding wire is consumed per metric
tonne of reinforcement steel
| Is This Answer Correct ? | 12 Yes | 0 No |
Answer / chandra kesh singh
6-8 kg binding wire is required for 1
metric tonne steel
| Is This Answer Correct ? | 6 Yes | 2 No |
Answer / st.subramani
Binding wire required for 8 to 10 kg per ton of steel.
| Is This Answer Correct ? | 3 Yes | 2 No |
Answer / smruti
Aproximately 6 kg to 9 kg of binding wire is required for
1MT of steel.
| Is This Answer Correct ? | 3 Yes | 3 No |
what is w/c ratio in dry lean concrete for m10 mix design
How its coming concrete grade M 20 means 1:2:4. how it coming 1:2:4.
1)What is swear, swage and storm water? 2)What are the sizes of bricks based on Nominal, practical and standard? 3) What is the distinguies between the grade of cement 43, 53?
How much paint is required for 1sqm.?how to calculate the paint...?
1 Answers MRKR, Sumadhura Infracon,
Why use of fly ash in cement
how to calculate 1:5:8 ratio concrete cement, sand, metal and water please give me brief calculation
The difference between Centering & Shuttering is –––
57. Calculate the volume of a truck loaded with stone chips whose data are as follows– 5 Top Length - 13-9, 13-10, 13-09 Bottom Length - 13-11, 13-10.5, 13-10 Top width - 8-7.5, 8-8, 8-7 Bottom width - 8-7, 8-8, 8-7.5 Depth - 2-0, 1-11.5, 1-10, 1-11, 1 -10.5, 1-11.75, 1-11
what is the cost differene of a same structure when it is constructed with brick masonary, and when it is constructed with concrete as a frame structure.????????
What is the diffrence between plinth/basement and plot area
What is the benefit of making a cantiliver proped.?
7 Answers CCCL, Engineers India Limited,
what is the minium content of cementous material per cu meter
Civil Engineering (5086)
Mechanical Engineering (4453)
Electrical Engineering (16638)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)