I'm puting roof slab M20 Design Concrete,Twoway slab how
many days wait for remooving of shuttering?
Answer Posted / maheswaran
After 7 days
| Is This Answer Correct ? | 3 Yes | 11 No |
Post New Answer View All Answers
Can we weld hot rolled steel ASTM A615 ? Please Give the detail answer please thanks alot
How to calculate density of 40 mm coarse aggregate, in mixing ration 1:1.5:3? Please explain calculation for density
Does VDF add strength to the flooring apart from preventing water ingress?
what is the max. area can we apply the plate load test ?
how clculate excavated or backfilling quantity by simpson's rule
Use of coping on terrace wall and in 4" wall is compulsory or not ?
Explain the latest method to detect a crack in a building?
What in your past experience or education prepares you for the position for which you are applying
How to calculate or what is the process of calculation for making 1Metre squre area by AAC Blok which quantity of Cement, Sand & Chips are to be required?
i have boiler of 35 tone and wanted dig out foundation is there any body to help me to carry out calculation for the foundation like
Can we use the flyash bricks in brick bat coba?
How to do rate analysis for concrete work including shuttering work?
While calculating the weight of the steel per running meter, the formula used is [(dxd)/162]. Why 162 is used in denominator & how it is derived?
specifications of fe500 steel
how many time use of plywood shuttering and IS code