I'm puting roof slab M20 Design Concrete,Twoway slab how
many days wait for remooving of shuttering?

Answers were Sorted based on User's Feedback



I'm puting roof slab M20 Design Concrete,Twoway slab how many days wait for remooving of shut..

Answer / k chiranjeevulu

to remove shuttering after 14 days

Is This Answer Correct ?    32 Yes 6 No

I'm puting roof slab M20 Design Concrete,Twoway slab how many days wait for remooving of shut..

Answer / sasi

after 14 days

Is This Answer Correct ?    17 Yes 5 No

I'm puting roof slab M20 Design Concrete,Twoway slab how many days wait for remooving of shut..

Answer / mahendra mohan srivastava

hallo my dear friendrs
If slab is less then 4.5 m then we remove shuttring after 7
days and if grater then 4.5 m then we remove shuttring
after 14 days not the strength of concrete.

Is This Answer Correct ?    13 Yes 1 No

I'm puting roof slab M20 Design Concrete,Twoway slab how many days wait for remooving of shut..

Answer / koti reddy allu

Hi Veeramani, it's Reddy here. First of all the basic
criteria for De shuttering is 1. Type of formwork i.e.
Vertical Form work for Columns, Soffit form work for
Slabs/Bems etc 2. The Effective Span of the member

Deshuttering period neither depends on Grade nor Depends on
Curing period according to IS 456 - 2000.

Is This Answer Correct ?    9 Yes 1 No

I'm puting roof slab M20 Design Concrete,Twoway slab how many days wait for remooving of shut..

Answer / baskar

7 days

Is This Answer Correct ?    3 Yes 0 No

I'm puting roof slab M20 Design Concrete,Twoway slab how many days wait for remooving of shut..

Answer / nagori salim

Completely depends upon Grade of Concrete

Higher the Grade, Lesser will be the period for deshuttering

Is This Answer Correct ?    7 Yes 6 No

I'm puting roof slab M20 Design Concrete,Twoway slab how many days wait for remooving of shut..

Answer / tanvir , faridabad

it should be removed in 28 days in winters , in summer it
can be open in 22 days

Is This Answer Correct ?    5 Yes 4 No

I'm puting roof slab M20 Design Concrete,Twoway slab how many days wait for remooving of shut..

Answer / veeramani amanthan

what will be the concrete strength attained in 7, 14, & 28
days please clear

Is This Answer Correct ?    2 Yes 1 No

I'm puting roof slab M20 Design Concrete,Twoway slab how many days wait for remooving of shut..

Answer / vipin sharma

As per IS 456:2000, the slab shuttering can be removed
after 3 days but immediate after removal of shuttering
proping of the slab need to be done and for beam the
shuttering can be removed after 7 days subject to proping.
Advisable
slab shuttering removal- 7days
Beam bottom less than 6 meter- 14 days
Beam bottom greater than 6 meter- 21days

Is This Answer Correct ?    3 Yes 2 No

I'm puting roof slab M20 Design Concrete,Twoway slab how many days wait for remooving of shut..

Answer / s.prabhu

as per IS456 Centering deshuttering period is depends upon
the span of the beam / slab.

Span less than or equal to 3m is 14days

Span more than 3m is 21 days.



Regads
S.PRabhu
9901702081

Is This Answer Correct ?    2 Yes 1 No

Post New Answer

More Civil Engineering Interview Questions

difference between deep and shallow well?

7 Answers  


What is differnce between founadation & footin ?

5 Answers  


RCC MEANS

7 Answers  


Why sea sand and desert sand are dont used for construction

1 Answers  


which "s the best wood for commercial purpose?

4 Answers  






Is there any codal provision stating the actual diameter for chair bars?

1 Answers   CADS Software,


sir i want to know that in L & T construction can we do our 6 months training proggramme cum placement???????

0 Answers   L&T,


what is idealized curve for concrere and steel

0 Answers   CSIL,


How many layers in 12mm and 18mm plywood?

6 Answers   JMC Projects, L&T,


What is the specific weight of sand?

14 Answers  


how many cement bag in 1m*m*m

33 Answers  


cement, sand, aggregate,reinforcement & concrete consumption per square feet in multi storeyed building

0 Answers  


Categories
  • Civil Engineering Interview Questions Civil Engineering (5085)
  • Mechanical Engineering Interview Questions Mechanical Engineering (4451)
  • Electrical Engineering Interview Questions Electrical Engineering (16632)
  • Electronics Communications Interview Questions Electronics Communications (3918)
  • Chemical Engineering Interview Questions Chemical Engineering (1095)
  • Aeronautical Engineering Interview Questions Aeronautical Engineering (239)
  • Bio Engineering Interview Questions Bio Engineering (96)
  • Metallurgy Interview Questions Metallurgy (361)
  • Industrial Engineering Interview Questions Industrial Engineering (259)
  • Instrumentation Interview Questions Instrumentation (3014)
  • Automobile Engineering Interview Questions Automobile Engineering (332)
  • Mechatronics Engineering Interview Questions Mechatronics Engineering (97)
  • Marine Engineering Interview Questions Marine Engineering (124)
  • Power Plant Engineering Interview Questions Power Plant Engineering (172)
  • Textile Engineering Interview Questions Textile Engineering (575)
  • Production Engineering Interview Questions Production Engineering (25)
  • Satellite Systems Engineering Interview Questions Satellite Systems Engineering (106)
  • Engineering AllOther Interview Questions Engineering AllOther (1379)