I'm puting roof slab M20 Design Concrete,Twoway slab how
many days wait for remooving of shuttering?
Answers were Sorted based on User's Feedback
Answer / mahendra mohan srivastava
hallo my dear friendrs
If slab is less then 4.5 m then we remove shuttring after 7
days and if grater then 4.5 m then we remove shuttring
after 14 days not the strength of concrete.
| Is This Answer Correct ? | 13 Yes | 1 No |
Answer / koti reddy allu
Hi Veeramani, it's Reddy here. First of all the basic
criteria for De shuttering is 1. Type of formwork i.e.
Vertical Form work for Columns, Soffit form work for
Slabs/Bems etc 2. The Effective Span of the member
Deshuttering period neither depends on Grade nor Depends on
Curing period according to IS 456 - 2000.
| Is This Answer Correct ? | 9 Yes | 1 No |
Answer / nagori salim
Completely depends upon Grade of Concrete
Higher the Grade, Lesser will be the period for deshuttering
| Is This Answer Correct ? | 7 Yes | 6 No |
Answer / tanvir , faridabad
it should be removed in 28 days in winters , in summer it
can be open in 22 days
| Is This Answer Correct ? | 5 Yes | 4 No |
Answer / veeramani amanthan
what will be the concrete strength attained in 7, 14, & 28
days please clear
| Is This Answer Correct ? | 2 Yes | 1 No |
Answer / vipin sharma
As per IS 456:2000, the slab shuttering can be removed
after 3 days but immediate after removal of shuttering
proping of the slab need to be done and for beam the
shuttering can be removed after 7 days subject to proping.
Advisable
slab shuttering removal- 7days
Beam bottom less than 6 meter- 14 days
Beam bottom greater than 6 meter- 21days
| Is This Answer Correct ? | 3 Yes | 2 No |
Answer / s.prabhu
as per IS456 Centering deshuttering period is depends upon
the span of the beam / slab.
Span less than or equal to 3m is 14days
Span more than 3m is 21 days.
Regads
S.PRabhu
9901702081
| Is This Answer Correct ? | 2 Yes | 1 No |
What is difference between nominal mix and design mix?
In your experience what is the maximum beam length. What's beam size and also please provide column size also. Thanks.
Why provides hook of stirrups only ones side?
What is the per cu. mt. price of ready mix in Gujarat region.?
calculation of quantities of cement and sand in 1cum mortar with 1:6 ratio
How many bricks,sand,cement in 1m3 bricks masonary
how to take the quantity of block work and plastering 1block price:3saudi riyal cement:1bag:15 saudi riyal sand:3bag:20 saudi riyal 1mason:9hour per hour 40 saudi riyal 1labour:9hour per hour 40 saudi riyal can anybdy calculate
how will calculate 4"thick solid block quantities 1m3 sand cement ratio and breack up detail
Explain the water bound macadam roag
How much overlapping required for welding the reinforcement bars in Columns & beams
WHAT IS THE IMPORTANCE OF FLY ASH BRICK?
Explain why concrete barriers have curved surface profiles?
Civil Engineering (5086)
Mechanical Engineering (4456)
Electrical Engineering (16639)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)