Answer / r. ashok kumar
Yes we can change the number of work process in RZ10. But to
get into use of newly created work process, We should
restart the Application Server.
Is This Answer Correct ? | 6 Yes | 2 No |
Answer / imran
RZ04 is used to define operation modes
and the distribution can be changed in SM63
Is This Answer Correct ? | 3 Yes | 0 No |
Answer / naveen
The procedure to make more work processes available is implemented in two stages:
Reserved (restricted) work processes:
In addition to familiar work process types (dialog, background, spool, and so on), there is also the type reserved. The number of initial work processes (as with the other types also) is specified in the profile parameter rdisp/wp_no_restricted. No further reserved WPs can be created while the system is running.
Reserved work processes are always of the dialog type. They are kept free in normal operation and not used until the system identifies a bottleneck and needs additional work processes to remove it.
Work processes started dynamically If the dynamic work processes are active (rdisp/dynamic_wp_check=TRUE), the system can start new work processes up to the limit specified in rdisp/wp_max_no in order to resolve deadlocks. Dynamic work processes can have different types (dialog, batch, update, and so on).
No reserved work processes are configured in the standard setting (rdisp/no_restricted = 0), but up to two work processes can be started dynamically rdisp/max_wp_no=<Sum of all configured WPs + 2>).
The values would be stranded 2 to 600 wp
This can be changed in RZ11
Newly added parameters:
rdisp/wp_no_restricted
rdisp/wp_max_no
rdisp/dynamic_wp_check
rdisp/max_dynamic_wp_alive_time
rdisp/configurable_wp_no
Is This Answer Correct ? | 3 Yes | 0 No |
Answer / sudheer.y
Through RZ04 you can increase and decrease the DIA & BG
Processes in ECC6-Sudheer-TechM
Is This Answer Correct ? | 9 Yes | 13 No |
Answer / ganesh varma
Yes, we can by using the Transaction RZ11.
In RZ11 most of the parameters doesn't require restart of
the system.
Is This Answer Correct ? | 3 Yes | 7 No |
What is Consolidation route and delivery routes?
How can you define login policy for users in sap system?
How to configure regular transactions such as MM01 to view archived data?
how to send the out put of a background job to only 10 users?
what is ECC ? what is the main difference between ECC and other older verssions of SAP ?
how to find the ip address of system on solaries at os level
What is the purpose of tdevc ?
while applying patches with jspm java engine restarts while the jspm is still running.how?
how can u see the version of the profile in sap
Hi there, Can any one suggest me a good SAP-BASIS training institute near Koramangala In Bangalore.
Transport error codes and their description?
Mention what is the difference between central instance & application server?