what is right time of slab DE shattering and beam boo tam.
Answers were Sorted based on User's Feedback
Answer / map
It depends up on span of the beam normally after 7 days we can remove shuttering and support with props.
| Is This Answer Correct ? | 24 Yes | 4 No |
Answer / azam
The time of slab deshutting after getting 67% strength at 4 or 7 days same for beam bottom and it also depend of span of beam.
| Is This Answer Correct ? | 21 Yes | 3 No |
as per IS 456 beam bottome should be remove after 14 days.
concrete strength is more than 70%. if span is more than 11
mt then its remove after 21 days.
| Is This Answer Correct ? | 12 Yes | 1 No |
Answer / sahilshah.civil@gmail.com
As per IS 456:2000
a) Columns/vertical member : 16-24 hrs
b) Slab - 3 day - prop to be kept below
c) Beam - 7 day - prop to be kept below
props to slab
a) spanning up to 4.5 m = 7 day
b) spanning over 4.5 m = 14 day
props to beam
a) spanning up to 6 m = 14 days
b) spanning over 6 m = 21 day
| Is This Answer Correct ? | 3 Yes | 0 No |
Answer / mitesh patel
Beam Sides can be allowed to be removed on the next day of
casting.
Bottoms should be allowed only after 7 days of casting.
This is practical answer on site otherwise contractors will
run away.
| Is This Answer Correct ? | 1 Yes | 0 No |
Answer / ananth
span length below 4.5m 7 days
span length over 4.5m 14days
| Is This Answer Correct ? | 1 Yes | 0 No |
Answer / md nezam
DE shattering can be done for slab bottom after 3days and Beam bottom after 7 day,but immediately props to be refixed.
| Is This Answer Correct ? | 3 Yes | 3 No |
Answer / sagar tiwari
span length over 6m than 28 days
span length below 6m than 14 days
span length over 4.5m than 14 days
span length below 4.5m than 7 days
| Is This Answer Correct ? | 0 Yes | 0 No |
Answer / vinaysagar donakanty
The above answer were right but it is advisable to check strength of cubes at 3 days or 7 days or 14 days before deshuttering.
| Is This Answer Correct ? | 0 Yes | 0 No |
how much cement,sand,aggregate will use for 1 cum in ratio of 1:2:4.
16 Answers ARS, College School Exams Tests, Gulf Construction, HRL, mWorkspace, NCC, URC Construction,
which is cover of r.c.c. column,beam and slab
1 cft of brickwork 1:6 mortar ratio need 12 numbers of bricks so find the quantity of sand and number of cement bags
Can compresive strength test for concrete at 1 day age possible to carry out? If yes, which IS code describes the procedure for such testing?
difference b/w stress and strength
IS sobha developers ,bangalore an good place to work for the freshers
How to calculate the cement and fine aggregate requirement for solid block masonry works in terms of Sqm. 1. 400x200x200mm 2. 400x200x100mm 3. 600x200x100mm 4. 600x200x200mm I need the answer for 1 Sqm of solid block works.
What is the release of lien?
what is diffence in grade 43 & 53 of cement?
4 Answers KFC, L&T, NICE, Puravankara,
in the earthquqke the profile of water on dam is parabolic or not
How many modular bricks are required for 1 cubic meter of brick masonry?
14 Answers ITI, L&T,
What is the 162 in steel weight formula?
Civil Engineering (5086)
Mechanical Engineering (4456)
Electrical Engineering (16639)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)