what is right time of slab DE shattering and beam boo tam.
Answers were Sorted based on User's Feedback
Answer / map
It depends up on span of the beam normally after 7 days we can remove shuttering and support with props.
| Is This Answer Correct ? | 24 Yes | 4 No |
Answer / azam
The time of slab deshutting after getting 67% strength at 4 or 7 days same for beam bottom and it also depend of span of beam.
| Is This Answer Correct ? | 21 Yes | 3 No |
as per IS 456 beam bottome should be remove after 14 days.
concrete strength is more than 70%. if span is more than 11
mt then its remove after 21 days.
| Is This Answer Correct ? | 12 Yes | 1 No |
Answer / sahilshah.civil@gmail.com
As per IS 456:2000
a) Columns/vertical member : 16-24 hrs
b) Slab - 3 day - prop to be kept below
c) Beam - 7 day - prop to be kept below
props to slab
a) spanning up to 4.5 m = 7 day
b) spanning over 4.5 m = 14 day
props to beam
a) spanning up to 6 m = 14 days
b) spanning over 6 m = 21 day
| Is This Answer Correct ? | 3 Yes | 0 No |
Answer / mitesh patel
Beam Sides can be allowed to be removed on the next day of
casting.
Bottoms should be allowed only after 7 days of casting.
This is practical answer on site otherwise contractors will
run away.
| Is This Answer Correct ? | 1 Yes | 0 No |
Answer / ananth
span length below 4.5m 7 days
span length over 4.5m 14days
| Is This Answer Correct ? | 1 Yes | 0 No |
Answer / md nezam
DE shattering can be done for slab bottom after 3days and Beam bottom after 7 day,but immediately props to be refixed.
| Is This Answer Correct ? | 3 Yes | 3 No |
Answer / sagar tiwari
span length over 6m than 28 days
span length below 6m than 14 days
span length over 4.5m than 14 days
span length below 4.5m than 7 days
| Is This Answer Correct ? | 0 Yes | 0 No |
Answer / vinaysagar donakanty
The above answer were right but it is advisable to check strength of cubes at 3 days or 7 days or 14 days before deshuttering.
| Is This Answer Correct ? | 0 Yes | 0 No |
Please tell me vasthu room sizes. Thanks.
plumbing CPVC fitting FTE Brass full form
what is the formular for measuring minimum depth of a foundation
what is the max diameter of bar will provided in 100 mm thick slab
How to Rectify deep crack formed on Brick Wall? Explain the method of rectify the defect?
What is difference between limit state and working stress method? How it is applies in building structure.
what is the criteria for the finalisation of pavement thickness in road project?
how to Concrete cubes testing curing time 7 days casting date 24.05.17 testing date ?
What is the Systematic Responsibility Site Engineer? Who are the above and under co-oridinating ? What is office & Site co-ordination of Site Engineer?
How to find the cement, sand, Aggregate, for m20, m25 grade of concrete..?
what is the thikness of binding wire please quick response
shear stress where is max.min in beams?
Civil Engineering (5086)
Mechanical Engineering (4456)
Electrical Engineering (16639)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)