Golgappa.net | Golgappa.org | BagIndia.net | BodyIndia.Com | CabIndia.net | CarsBikes.net | CarsBikes.org | CashIndia.net | ConsumerIndia.net | CookingIndia.net | DataIndia.net | DealIndia.net | EmailIndia.net | FirstTablet.com | FirstTourist.com | ForsaleIndia.net | IndiaBody.Com | IndiaCab.net | IndiaCash.net | IndiaModel.net | KidForum.net | OfficeIndia.net | PaysIndia.com | RestaurantIndia.net | RestaurantsIndia.net | SaleForum.net | SellForum.net | SoldIndia.com | StarIndia.net | TomatoCab.com | TomatoCabs.com | TownIndia.com
Interested to Buy Any Domain ? << Click Here >> for more details...


what is right time of slab DE shattering and beam boo tam.

Answers were Sorted based on User's Feedback



what is right time of slab DE shattering and beam boo tam...

Answer / map

It depends up on span of the beam normally after 7 days we can remove shuttering and support with props.

Is This Answer Correct ?    24 Yes 4 No

what is right time of slab DE shattering and beam boo tam...

Answer / azam

The time of slab deshutting after getting 67% strength at 4 or 7 days same for beam bottom and it also depend of span of beam.

Is This Answer Correct ?    21 Yes 3 No

what is right time of slab DE shattering and beam boo tam...

Answer / ronak shah

as per IS 456 beam bottome should be remove after 14 days.
concrete strength is more than 70%. if span is more than 11
mt then its remove after 21 days.

Is This Answer Correct ?    12 Yes 1 No

what is right time of slab DE shattering and beam boo tam...

Answer / sahilshah.civil@gmail.com

As per IS 456:2000

a) Columns/vertical member : 16-24 hrs
b) Slab - 3 day - prop to be kept below
c) Beam - 7 day - prop to be kept below

props to slab
a) spanning up to 4.5 m = 7 day
b) spanning over 4.5 m = 14 day

props to beam
a) spanning up to 6 m = 14 days
b) spanning over 6 m = 21 day

Is This Answer Correct ?    3 Yes 0 No

what is right time of slab DE shattering and beam boo tam...

Answer / mitesh patel

Beam Sides can be allowed to be removed on the next day of
casting.
Bottoms should be allowed only after 7 days of casting.
This is practical answer on site otherwise contractors will
run away.

Is This Answer Correct ?    1 Yes 0 No

what is right time of slab DE shattering and beam boo tam...

Answer / ananth

span length below 4.5m 7 days
span length over 4.5m 14days

Is This Answer Correct ?    1 Yes 0 No

what is right time of slab DE shattering and beam boo tam...

Answer / md nezam

DE shattering can be done for slab bottom after 3days and Beam bottom after 7 day,but immediately props to be refixed.

Is This Answer Correct ?    3 Yes 3 No

what is right time of slab DE shattering and beam boo tam...

Answer / sagar tiwari

span length over 6m than 28 days
span length below 6m than 14 days

span length over 4.5m than 14 days
span length below 4.5m than 7 days

Is This Answer Correct ?    0 Yes 0 No

what is right time of slab DE shattering and beam boo tam...

Answer / vinaysagar donakanty

The above answer were right but it is advisable to check strength of cubes at 3 days or 7 days or 14 days before deshuttering.

Is This Answer Correct ?    0 Yes 0 No

what is right time of slab DE shattering and beam boo tam...

Answer / r.ranjith kumar

slab de shetting 2 day

Is This Answer Correct ?    0 Yes 3 No

Post New Answer

More Civil Engineering Interview Questions

Please tell me vasthu room sizes. Thanks.

0 Answers  


plumbing CPVC fitting FTE Brass full form

0 Answers   RK,


what is the formular for measuring minimum depth of a foundation

3 Answers  


what is the max diameter of bar will provided in 100 mm thick slab

1 Answers   Guru Tech,


How to Rectify deep crack formed on Brick Wall? Explain the method of rectify the defect?

3 Answers   Coromandel,


 What is difference between limit state and working stress method? How it is applies in building structure.

0 Answers  


what is the criteria for the finalisation of pavement thickness in road project?

1 Answers  


how to Concrete cubes testing curing time 7 days casting date 24.05.17 testing date ?

0 Answers  


What is the Systematic Responsibility Site Engineer? Who are the above and under co-oridinating ? What is office & Site co-ordination of Site Engineer?

0 Answers  


How to find the cement, sand, Aggregate, for m20, m25 grade of concrete..?

1 Answers   Afcons, L&T,


what is the thikness of binding wire please quick response

9 Answers   Omaxe,


shear stress where is max.min in beams?

2 Answers  


Categories
  • Civil Engineering Interview Questions Civil Engineering (5086)
  • Mechanical Engineering Interview Questions Mechanical Engineering (4456)
  • Electrical Engineering Interview Questions Electrical Engineering (16639)
  • Electronics Communications Interview Questions Electronics Communications (3918)
  • Chemical Engineering Interview Questions Chemical Engineering (1095)
  • Aeronautical Engineering Interview Questions Aeronautical Engineering (239)
  • Bio Engineering Interview Questions Bio Engineering (96)
  • Metallurgy Interview Questions Metallurgy (361)
  • Industrial Engineering Interview Questions Industrial Engineering (259)
  • Instrumentation Interview Questions Instrumentation (3014)
  • Automobile Engineering Interview Questions Automobile Engineering (332)
  • Mechatronics Engineering Interview Questions Mechatronics Engineering (97)
  • Marine Engineering Interview Questions Marine Engineering (124)
  • Power Plant Engineering Interview Questions Power Plant Engineering (172)
  • Textile Engineering Interview Questions Textile Engineering (575)
  • Production Engineering Interview Questions Production Engineering (25)
  • Satellite Systems Engineering Interview Questions Satellite Systems Engineering (106)
  • Engineering AllOther Interview Questions Engineering AllOther (1379)