what is right time of slab DE shattering and beam boo tam.
Answer Posted / ronak shah
as per IS 456 beam bottome should be remove after 14 days.
concrete strength is more than 70%. if span is more than 11
mt then its remove after 21 days.
Is This Answer Correct ? | 12 Yes | 1 No |
Post New Answer View All Answers
what will happen if one could not properly follow the spacing of slab reinforcement bar?
What is a kip?
How did street originate in the plumbing term street ell?
For plate load test why we are applying pressure 3 times the proposed allowable bearing pressure? Is there any supporting standards for this?
What is the tensile strength of wood?
what is the Asfalt test?in road constraction..?
How to arrive dry volume of concrete (1.52 to 1.57) ?
how i can tak Quantity of mortar in block work
Which stone is best for wall construction Laterite Stone or Cement Blocks
(Project Management Topic) What are the important criteria in the successful realization of the project?
Can a wave happen in the middle of the ocean like in the movie poseidon 2006?
what is that one cub metre plaster in cemant and fine sand
what is anchorage length,lap length and (dont remember the last one)
what discoveries did you have in relation to your course?
What are the materials used in building a gravity dam?