what is right time of slab DE shattering and beam boo tam.

Answer Posted / ronak shah

as per IS 456 beam bottome should be remove after 14 days.
concrete strength is more than 70%. if span is more than 11
mt then its remove after 21 days.

Is This Answer Correct ?    12 Yes 1 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

what will happen if one could not properly follow the spacing of slab reinforcement bar?

1570


What is a kip?

712


How did street originate in the plumbing term street ell?

623


For plate load test why we are applying pressure 3 times the proposed allowable bearing pressure? Is there any supporting standards for this?

1336


What is the tensile strength of wood?

648






what is the Asfalt test?in road constraction..?

1640


How to arrive dry volume of concrete (1.52 to 1.57) ?

1898


how i can tak Quantity of mortar in block work

1977


Which stone is best for wall construction Laterite Stone or Cement Blocks

1310


(Project Management Topic) What are the important criteria in the successful realization of the project?

1658


Can a wave happen in the middle of the ocean like in the movie poseidon 2006?

684


what is that one cub metre plaster in cemant and fine sand

1510


what is anchorage length,lap length and (dont remember the last one)

1729


what discoveries did you have in relation to your course?

1652


What are the materials used in building a gravity dam?

638