what is right time of slab DE shattering and beam boo tam.
Answer Posted / mitesh patel
Beam Sides can be allowed to be removed on the next day of
casting.
Bottoms should be allowed only after 7 days of casting.
This is practical answer on site otherwise contractors will
run away.
| Is This Answer Correct ? | 1 Yes | 0 No |
Post New Answer View All Answers
what is the minimum cement content for M20 & M25 as per is code -456(2000).
What is hybrid foundation?
Define What glue is least sticky?
density of crush sand & crush stone or grit powder
What is thumb rule in quantity and cost estimation of a residential building in civil engineering??
though u r a civil engineer, y r u interested in tcs???
i have to give lap joint fo 1Mtr steel of dia12mm,whenever i did mistake i cut less 5cm plz tell me how much i will give lap joint so that length comes 1Mtr
Can anybody explain with the help of sketeches that what are 2legged , four legged & 6legged stirrups and how to calculate cut length of diamond ring(stirrups)?
Civil engineering related
what should be RCC material i.e iron rod(mm)x cement x stone x sand for laying of slab L 42'x B 22'x tk 0.375ft = 1nos & column of H 17'x15"x8" 2nos.
How to calculate Acctually Brickwork Quantity in Honey Comb Brick in circular Soak Pit
How do we test on design and style in a software?
what is the types of door's wood?
Can any body help me out by telling hoe swelling pressure test of soil is carried out ? some body told me the procedure & formula (change in length /116.3*100%) but still i am confused ? pls help.
afe or not