what is right time of slab DE shattering and beam boo tam.
Answer Posted / sahilshah.civil@gmail.com
As per IS 456:2000
a) Columns/vertical member : 16-24 hrs
b) Slab - 3 day - prop to be kept below
c) Beam - 7 day - prop to be kept below
props to slab
a) spanning up to 4.5 m = 7 day
b) spanning over 4.5 m = 14 day
props to beam
a) spanning up to 6 m = 14 days
b) spanning over 6 m = 21 day
| Is This Answer Correct ? | 3 Yes | 0 No |
Post New Answer View All Answers
What is the wall thickness of NP-3&NP-4 hume pipe as per I.S code
How much river sand contain the 6 & 10 wheeler truck? Or Maximum sand that any type of truck carry?
How to check slab shuttering level.? Or check list for slab ?
What do you meant by gui?
Please tell me any one, how many quantity concrete paver block fixing perday ( 8hours) per mason??
How to calculate dry of volume of concrete constant?How it comes 1.54 or 1.57
Use of coping on terrace wall and in 4" wall is compulsory or not ?
What is thumb rule for deep trench excavation
what is yield and tensile strength of steel, if steel has yeilding strength of 60 psi than how much its tensile strength?
The mixture of different ingredients of cement is burnt at?
what is the max. and mim. height of vertical post in informatry sign board which is used in highway projects.
what is the metal ratio in granular subbase coarse for one cum ? And please explain the morth table ...what is the difference between grading 1 , 2, 3 what it means..plz explain
If we are providing concrete joint in every 10m with water stopper in water tank wall then is it necessary to cut the steel at joint section?
Can we use Polystyrene as a Bitumen modifier !! if so is it a good MS research topic ? and what type of laboratory tests will be conducted during Research work ??
How do we test on design and style in a software?