Answer / pavan
WEIR: an impervious barrier which is constructed across a
river to raise the water level on the upstream side is known
as a weir. Here the water level is raised up to the required
height and the surplus water is allowed to flow over the
weir. Generally it is constructed across an inundation river.
BARRAGE: when adjustable gates are installed over a weir to
maintain the water surface at different levels at different
times is known as a barrage. The water level is adjusted by
operating the gates or shutters. The gates are placed at
different tiers and these are operated by cables from the
cabin. The gates are supported on piers at both ends. The
distance between the pier to pier is known as Bay.
| Is This Answer Correct ? | 95 Yes | 9 No |
Answer / anand
WEIR IS A STRUCTURE TO STORE WATER .AND WATER RAISES ABOVE
WEIR LEVEL IT OVERFLOW DUE TO GRAVTY.NO REQULATION OF
WATER IN THIS STRUCTURE.
iN BARRAGE WATER IS STORED AND REQULATED FOR IRRIGATION AND
POWER GENERATION THROUCH GATES.
| Is This Answer Correct ? | 68 Yes | 21 No |
Answer / sofia
weir is an impervious barrier .here water level is rise up
to the required hight & the surplus water is allowed to
flow over the weir...........but in case of barrage
adjustable gates are installed...........
| Is This Answer Correct ? | 51 Yes | 11 No |
Answer / pinakin
Gated weir is called a barrage..Barrage works on elevated
crest and water flow is controlled using gates..
Weir is the construction where all work is done by elevated
crest.Water flow is not controlled to great extent.
Now days usually barrages are constructed because water flow
can be controlled easily.
Elevation/ht. of crest is low in barrage than weir.
| Is This Answer Correct ? | 22 Yes | 5 No |
Answer / iftikhar azim
if the major part of the ponding or the entire ponding of
water, ponding means to block or store water, is done by
the crest and the nil par or smaller part is done by the
shutters, such type of barrier is known as WEIR. But if the
major part of the ponding is done by gates and smaller part
by the crest, then it is called a BARRAGE OR RIVER
REGULATOR.
| Is This Answer Correct ? | 12 Yes | 2 No |
Answer / charu
weir is a free flow water from dam.. barage is through gate..
| Is This Answer Correct ? | 16 Yes | 10 No |
Answer / rohit gupta
Weir is a uncontrolled storage structure....
barrage is a controlled storage structure having gates installed in it...
| Is This Answer Correct ? | 9 Yes | 4 No |
Answer / bharti sharma
if the major part or the entire ponding of water is achieved
by a raised crest and a smaller part or nil part of it is
achieved by a shutters,then this barrier is known as a weir.
if most of the ponding is done by gates and a smaller or nil
part of it is done by the raised crest,then the barrier is
known as a barrage.
| Is This Answer Correct ? | 7 Yes | 3 No |
Answer / bhupendra singh
weir - it is used to measure more discharge of a liquid.
barrage - water is stored and required for irrigation and power generations through gates.
| Is This Answer Correct ? | 5 Yes | 3 No |
Answer / aychilum
***Weirs are overflow structures built
across open channels to measure
the volumetric rate of water flow
***The crest of a measurement weir i s
usually perpendicular to the
direction of flow
| Is This Answer Correct ? | 1 Yes | 0 No |
why steel tanks are provided (a) for water pressure (b) for wind pressure (c) for earthquake pressure
How do I calculate the ground is resested for a 5 floor building?
what is C50 expressed in kg/m3
If the proportions of concrete is a:b:c i.e if "a" parts of cement,"b" parts of fine aggregate & "c" parts of coarse aggregate are mixed by volume. Then the resulting volume will have a volume of ------? How?
what is the procedure of plastering..?
Difference between lateral ties and stirrups?
for 1cum how much bag of cement is used for M20 grade
For the calculation of bearing pressure below the footing, to know whether it is below the safe bearing pressure of the soil, the unit of RCC below ground level to be taken is 25 KN/m3 or (25-15)KN/m3, where 25 is the unit weight of RCC and 15 is the unit weight of soil and whether the weight of backfilling to be taken?
what type of drawing used in the field construction?
que.is ideal size of bricnk use in india,joint size of mortar in massinary ,how many bricks used in 1cum.how to test at site.what is the possition of marka used in bricks?
what is the unit weight of steel(kg/cum)& unit weight of concrete in(kg/cum)?
Are you having any structural design experience?
4 Answers Ajnara Group, Jeyam Homes, L&T,
Civil Engineering (5086)
Mechanical Engineering (4456)
Electrical Engineering (16639)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)