what is right time of slab DE shattering and beam boo tam.
Answer Posted / sagar tiwari
span length over 6m than 28 days
span length below 6m than 14 days
span length over 4.5m than 14 days
span length below 4.5m than 7 days
| Is This Answer Correct ? | 0 Yes | 0 No |
Post New Answer View All Answers
What do you mean by tolerance factor of concrete ?
What in your opinion makes you the most suitably qualified candidate for this post of civil engineering technician?
relation bet Coefficient consolidation Cv, time factor Tv, drainage path d, & time t is Cv=d2Tv/t Cv=d2t/Tv Cv=tTv/d2 Cv=Tv/td2
what is yield and tensile strength of steel, if steel has yeilding strength of 60 psi than how much its tensile strength?
What is the effect of a building collapse?
when it is noted "JAMB SIM" what is the term "SIM" and what does it mean?
Why M15 is replaced by M20 when ammendment are made in IS456 in 2000?
What are the ingredients of pre-stressed concrete?
How to calculate material and labor required for 100 m2 plaster?
For fine aggregate which is most suitable River sand or crusher sand & why ?
How much does it cost for a R.C.C cover slab of size (450mmX 600mmx 100mm) double rf net given in feets using hand mix concrete?
plumbing CPVC fitting FTE Brass full form
what is civil enginnering & what you need of this course?
How do you compute moisture correction using the parameters gathered from Nuclear Density Gauge Apparatus and the moisture contents results from the lab.?
what are the Task work of different labour.?