what is right time of slab DE shattering and beam boo tam.
Answer Posted / vinaysagar donakanty
The above answer were right but it is advisable to check strength of cubes at 3 days or 7 days or 14 days before deshuttering.
| Is This Answer Correct ? | 0 Yes | 0 No |
Post New Answer View All Answers
Design a reinforced concrete combined footing (rectangular) for two columns located 3.60 metres apart. The overall sizes of the columns are 40cm x 40cm and 69cm x 60cm and the loads on them are 1000 kn and 1500 kn respectively. The space available for the width of the footing is restricted to 180cm. The S.B.C. of the soil is 280 kn/mm2 use M15 concrete.
how i get all type of short type question answer about civil engg
Can we use the flyash bricks in brick bat coba?
how to calculate mivan shuttering matrial
how i can calculate the actual nos & size of steel to make 1000sqft. x 3"thick slab
What is absolute pressure? How absolute pressure is calculated?
What are segregation and bleeding?
Explain what is Critical Path Method (C.P.M)?
What applicable rate of wct in bihar
weight of 1 cft 10mm, 20mm, 40mm aggregate weight of 1cft course sand
What are the advantages and disadvantages of using plastic and timber fenders?
How to fix the reinforcement in footing shorter bar at bottom and longer fix at top.
Explain what is the difference between built area and super built up area?
if i used salt as a add mixture in concrete, then what will happen and what are the naturally available add mixtures.
How to calculate quanty of steel in four leg stirrups?