How to calculate the amount of Brick,cement & sand required
for 1 cum of 230mm thick brick work with ratio 1:5 please
give me an answer with detailed step

Answer Posted / zuber ahmed

Volume of Dry Mortar = 35% of volume of Brickwork

Volume of Mortar required = 0.35 + 1 = 1.35 cu.m.

Cement required = 1/6 X 1.35 = 0.225 cu.m. =6.8Bags

Sand required = 5/6 X 1.35 = 1.125 cu.m.

Bricks required = 500 Nos.

Is This Answer Correct ?    10 Yes 43 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

What is a projection line?

703


what is diversion?

1737


Where is the worlds longest elevator and how long is it?

685


How can we calculate 8- storied Madrasha Building pile capacity by taking SPT value at site?

1567


How can i do RCC rate analysis?

1241






what is spacing of wallar support of 3m column. the thickness of column is 0.25 m.

1733


3. What are the disadvantages of your present job, things you do not like about it?

2279


I was once rejected for US visa in early August. But now I'm going again for interview next week. What are the chances that I will faced the same VO????

1646


contractor receive 100 MT steel.after compliting the work the contractor refund 90 MT steel.How reconsilation of steel done?

1887


Please send me the qunty. of mason/labour required in each day for different type of civil construction work?please send me ans. in my mail.my mail id is (parthamitra086@gmail.com) or here.

1909


How to calculate Cement in bags ,sand in sqft and aggregate in sqft for 1cum M25 grade concrete

1268


What are the techniques to measure road difference?

751


What are the standard plastic limit/liquid limit/plasticityindex for differrent type of soils?

1970


suppose that  156000 sq.ft rcc work builtup are.how many % of brick work to rcc work.

2297


Minimum concrete cover in slabs, columns, beams, foundation and other st?

665