In an aggregate blending plant, water is sprayed before
blending is performed. If the fine content in aggregate is
as high as 25 %, will not the fines form into lumps / balls
and distribution will not be uniform ? Further, the fines
will stick onto the interior of pug mill and its content
will be low. The mixed material is stockpiled for weeks /
months before use. Will it not be better that blending is
done in dry condition, and water will be added only during
compaction at site. Please forward your comments and
suggestions.
No Answer is Posted For this Question
Be the First to Post Answer
How do we calculate absolute pressure?
what are the CAD software versions you have used?
12 Answers ERA, IES,
brick work 1cum kitne cft hote hai
For 1 cu m of concrete required 1.54 Cu m times dry volume. Pl give clarification of 1.54 factor
1 Answers RASA, Unity Infraprojects,
What is the strength of 150x150mm cube compared to 300x300mm concrete cube?? Why?
What the codes used for Rigid Pavement and Flexible pavement.
Cement consumption of one cubic meter of aerocon blocks masonry?
0 Answers Sathiapal Engineers,
koi bta sakta ha ka steel ko calculate krna ka full mathod pls
please give the detail design for the soring and shuttering for 8.5m deep excavation in the sandy soil for 25x10 rectangular streaches
What is pile foundation?
what is difference between 33, 43 and 53 grade cement..? which is more suitable for construction and why,..??
how to find the cement and sand quantity for wall plastering
Civil Engineering (5086)
Mechanical Engineering (4456)
Electrical Engineering (16639)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)