what is procedure to find the volume of material in M20
concrete?
Answers were Sorted based on User's Feedback
Answer / ajithprasa vd
M20 means 1 part cement , 1.5 part sand and 3 part aggregate
Cement 7.5 bag
Sand 0.5 M3
Aggregate o.85 M3
| Is This Answer Correct ? | 8 Yes | 1 No |
Answer / engineer harry mrar
403kg cement
.42cum sand
.84 aggregate
181 liter water
| Is This Answer Correct ? | 3 Yes | 1 No |
Answer / ashok sakhare
M20 ratio is 1:1.5:3
(i)Total motor wet = 1+1.5+3= 5.5
(a) Volume of aggregate = 35.5*1.57= 0.856m3 Dry motor/ Cum
(b) volume of sand =1.5/5.5*1.57= 0.3
428m3/ Cum ( Dry motor)
(c) volume of cement =1/5.5*1.57 =( Dry cement) 0.285m3*1440=399 kg.
399/50kg= 7.99bags/Cum
(note: 1.57 for 1m3 Dry motor)
| Is This Answer Correct ? | 1 Yes | 0 No |
Answer / muzammil ahmed
m20=1:1.5:3=5.5, dry mix for im3 is 1.57
1.57/5.5=0.285x30 = 8.5bags OR
=0.285x1500=428.18kg/50=8.55bags(cement)
=0.285x1.5 =0.427x35.28=15cft
=0.285x3 =0.855x35.28=31cft
| Is This Answer Correct ? | 0 Yes | 3 No |
Answer / i.rajamohamed. p.s.y.e.college
M20 ratio is 1:1.5:3( TAKE 20mm aggregate)
(i)add ratio= 1+1.5+3= 5.5
(a) volume of aggregate = 1\7*1.57 = 0.22m3
(b) volume of sand =1.5/7*1.57= 0.33m3
(c) volume of cement =3/7*1.57 = 0.67m3*1440=964 kg.
(note: 1.57 for 1m3 box)
| Is This Answer Correct ? | 5 Yes | 16 No |
Management diagram of your project isβββ
what is meant by concrete joints?
how did find the quantity of cement ,sand , and aggregate in concreat which is givan by volume
I am a civil engineering student and going to attend interview in this week in an IT company.Will they ask me questions about my area of interest or cs
I need model question papers for writing the Dubai municipality exam,for G+1
does the compressive strength of brick be more then 3.5 n/mm2 or 5 n/mm2?
Is there the dry coefficient of cement is constant?
what is the average steel consumption in multy storey building as a residential and commercial?
What is the strength of 1:6:12 mix?
how to tie 10 legged stirrups
for 16mm thick cement plastring 1:6 on 100 Sq.m.New brick work,the quantity of cement required is.
what is the minimum and maximum water cement ratio
Civil Engineering (5086)
Mechanical Engineering (4453)
Electrical Engineering (16638)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)