a)If column dimensions are 250*400mm , what will be
cutting length for 8mm stirrups and how to calculate it? b)
If beam dimensions are 200*400mm , beam coveris 25mm , slab
cover is 20mm , what will be the cutting length for
stirrups? c)Column dimensions are 250*400mm , reinf. is
12nos. bar of 16mm dia , stirrups provided are two legged,
what will be the length of each ring?
Regards
Answers were Sorted based on User's Feedback
Answer / er shailesh kr srivastava
A)CUTTING LENGTH FOR 8mm Strips=2(250+400-2*80-2*8+24*8)
2(650-160+22*8)
2(490+176)
=1332mm
same as for beam
| Is This Answer Correct ? | 6 Yes | 9 No |
Answer / ajay
sir , my name ajay kumar ,working on site i also had the
same problem of estimation , but sir ur answer was so nicely
explained , im very thank full to u for ur valuable and
precious information, sir can i no ur email id and no so i
can get some knowlege from u ?
my email -ajaykapse2@gmail.com
| Is This Answer Correct ? | 6 Yes | 10 No |
Answer / ram bhawan
2(A+B)+16*DIA OF STIRRUP BAR
A = INNER HEIGHT OF STIRRUP
B = INNER BREATH OF STIRRUPS
IF CLEAR COVER IS GIVEN (COVER GIVEN FROM STIRRUP NOT FROM
MAIN BAR)
| Is This Answer Correct ? | 2 Yes | 9 No |
Answer / silpa
250-25+8=233mm,
400-25+8=383mm
2(0.233+0383)+16*0.08=2.512m
| Is This Answer Correct ? | 9 Yes | 32 No |
Answer / anthony victor bernard
a)250-column cover both side+8*dia of rod
400-column cover both side+8*dia of rod
so cutting length is (.200+.350)*2+(2*5*.008)
=1.180 mts
(b)cutting length is (.150+.355)*2+(2*5*.008)
=1.090 mts
(c)cutting length is (.100+.350)*2+(2*5*.008)
=0.980 mts
| Is This Answer Correct ? | 11 Yes | 38 No |
a)250-column cover both side+8*dia of rod
400-column cover both side+8*dia of rod
so cutting length is (.250+.400)*2-.160+.128
=1.268 mts
same as (b)
| Is This Answer Correct ? | 37 Yes | 65 No |
How can calculate the number of bricks.....? Give me answer hurry uppppppppp
The designs required to construct a building are ––
General Knowledge 1. Which is the virus for SWINE Flu? Ans.H1N1 virus 2. Who is Paola Maino? a) Original Name of Sonia Gandhi. b) Mother Name of Sonia Gandhi c) An actress d) Christian Missionary 3. Who is Andy Moles? 4. Which state there is no scheduled caste seat for lok Sabha Assembly? CIVIL ENGINEERING 1. When was Indian road Congress (IRC) established? 2. What is the camber for Concrete Road? 3. What is the camber to be provided for Earth Road? 4. What is the ruling gradient to be provided for Plain roads? 5. What is the type of surveying to be used for deciding the alignment of hilly roads? 6. What is the condition on which Bernoulli law depends? 7. water is which type of fluid a)Newtonian b)Non- Newtonian c)Ideal d)Compressive 8. The law of continuity depends upon what factors? 9. In Plane Table surveying which is done first a) centering b)Leveling c)Orientation d)Centering and leveling simultaneously 10. Pavement width depends upon a)Type of terrain b) lane width c)Type of traffic 11. Which is costliest type of timber a) Sal b) Shish am c) Teak? 12. Which is timber used for making plywood a)Teak c) Bamboo fibers d)Common Timber 13. What is Veneering?
how to reduce size of column 450 x 750 to 230 x.... if it is cut in area of bathroom? means it appears in bathroon any shifting or any other option....building is g + 10 and the bathroom is at first floor...
why 50% more is assumed while calculating dry volume of coarse and fine aggregates in concrete calculations.whether 50% more is correct? How is it decided? whether the same is applicable to cement volume. Also what about cement mortar dr volume? How much more is to be considered for dry volume of mortar.
What is the biggest dam in america?
what is the material consumption of 1:2:4 by kilogram?
what is the painting co efficient of slope roof tiles?
PCC Road Min Grade M 30 for VR standard Mahatashtra load 30 KN. what should be thickness of pavement, width 4m what should be length of panel.
what are the ffactors you considered choosing the course?
How to rectify thermal cracks (2mm wide, 9mm deep aprx. ) developed in tremix finished concrete floor?
how much quantity of cement and sand required for construction of 10 cum brick work( Brick size 3"*4"*9"(Standard size ) an d for 10 cum construction of SSM (Size stone masonary) with Cm 1:6 for both.
11 Answers GRC, KEC, L&T, Techno Electric and Engineering, UPENN,
Civil Engineering (5086)
Mechanical Engineering (4456)
Electrical Engineering (16639)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)