Answer / anirban ghosh
spro - production - basic data - work center - capacity
planning - work center formulas -
(A) define the formula parameter (say to fetch value
from Routing)
(B) define the formula (say field value * 2 /60)&
release it to be used in WC, scheduling etc.
Is This Answer Correct ? | 6 Yes | 0 No |
Answer / murali
First define standard parameters in OP19 and define
formulas in OP21.
Is This Answer Correct ? | 2 Yes | 0 No |
Answer / vijay
1.First create the formula papameters which is used in formulas
2.create the formules using formula parameters
Is This Answer Correct ? | 0 Yes | 0 No |
What are mandatory fields for PP configuration
Suppose the client wants me the vacancy to be displayed on a website as well as ess. How should I do it?
What do you do to run MRP for just one MRP Controller?
Is it possible to convert a 'multiple bom' into a 'variant bom'?
How to attach a drawing for a material to bom ? Is it possible ?
Which BOM maintenance functions do you require (copy functions, mass changes, and so on)?
List out the activities carried out in production planning?
Describe different types of scrap. Where all different types of scrap can be maintained on SAP user screens?
What is the uses of production scheduling profile and what the configure have you done current project
0 Answers Cognizant, Patanjali Ayurved,
What is user exist, customer exist, where can be used
Tell me important of the Production scheduling profile what are the things have to maintain in this profile
What is Material status and which view of the material master it is available?