How to make a Budget?
How will the user find out whether the purchases are under Budget value?
How to take out project cost report?
Budget of Purchase Order can be routed through Internal orders.
The Process is
1. Created Project
2. Created WBS
3. Add budget to WBS and release it
4. Create Internal order and assign the WBS to it
And now you can use this Internal Order in your PO against the Item category F or K (as per your PO requirement).
User can run CJ31 with WBS element and analyse the PO/PR/Consumption against the WBS element.
There are several transactions to take the project cost.
KOB1/S_ALR_87013003 as the best.
GopalK
Is This Answer Correct ? | 2 Yes | 0 No |
Vendor has SAP ERP in the system. Buyer sent material to vendor. Vendor processes the material and sends the finished goods to Buyer. What is the process to be followed at Vendors ERP?
What is the source of error "not allowed" in case of custom movement type creation?
What is the movement type for return to vendor? How to reverse it?
How to create pr or po by mrp?
what are the types of info records?
Is there any special indicator to identify subcontract item in the material master?
How does 'automatic account assignment' work in mm?
How can I transfer the goods as consignment from plant to another plant ? Which configurations or set up should I maintain ?
how to define and assign standard purchasing organisation
What is the difference between valuated Stock and Non Valuated Stock?
10 Answers AGC, IBM, Reliance, TCS,
Name some of the internal SAP interfaces used between SAP MM IM and WM modules.
In the vendor consignment process what you have done in GR Process