How to make a Budget?
How will the user find out whether the purchases are under Budget value?
How to take out project cost report?
Answer Posted / sapmmgopal@gmail.com
Budget of Purchase Order can be routed through Internal orders.
The Process is
1. Created Project
2. Created WBS
3. Add budget to WBS and release it
4. Create Internal order and assign the WBS to it
And now you can use this Internal Order in your PO against the Item category F or K (as per your PO requirement).
User can run CJ31 with WBS element and analyse the PO/PR/Consumption against the WBS element.
There are several transactions to take the project cost.
KOB1/S_ALR_87013003 as the best.
GopalK
| Is This Answer Correct ? | 2 Yes | 0 No |
Post New Answer View All Answers
What are the lot size attributes a material can posses?
What are the procedure to create pr or po by mrp?
Please suggest ME which institute is best for sap mm and kindly let me know which institute Mr.Syed Quarish is working and his contact no? and who is expert in teaching test scrips and CIN
What is source list? What is the menu path to define a source list?
What is batch information cockpit?
How is subcontracting used in case of mm?
What are the important fields in purchasing view?
What is the procedure to make the source list automatically appear in material master as default if maintained at plant level using ome5?
Upto what extent we can increase the length of materials master short text.
You want to perform quota arrangement. What steps would you take?
what are the data contained in the information record?
What are the different sections in vendor master data?
How you can link a document to a vendor master record?
What are transactions that will cause a change in stock?
What is the procedure to delete materials permanently from material master?