What is planning file entry and Where can we use
Answer / hariskumaar
The first process in MRP is the checking of the planning file entry.
The planning run and the scope of the planning run (which materials are planned in which planning run) are controlled by the planning file.
The planning file contains a list of all materials relevant to the planning run. As soon as a material master record is created with MRP data and a valid MRP type, this material is then automatically included in the planning file.
During MRP run at plant level system checks for the materials which are having indicator activated in planning file and plans those materials and will not plan the materials for which this indicator is not activated….this reduces the run time of the MRP..
Is This Answer Correct ? | 1 Yes | 0 No |
List out the basic procedure for dispatching operations in capacity leveling?
What happens to planned after it has been converted into production order ?
Difference between Item categories or what is variable size item or non stock item.
What are all the 'sub-components' of production orders?
In implementation stage tell some standard scenario before AS-Is & TO-BE
What is the planning time fence?
What is Routing & rerouting
What do you do to run MRP for just one MRP Controller?
Can i create Production order without bom and routing ? lakshman
How mrp (material requirement planning) types are classified?
What is SOP and types of SOP?
What are the MRP master data?