what is the relation between the grid voltage and generator
voltage how to link up generator with grid
Answers were Sorted based on User's Feedback
Answer / muili ibrahim babatunde
This involves synchronization process. Hence, For the two voltages to link, these parameters must be met:
(1)Frequency ( Hz ) : The frequency of the voltages produced by the generator must be equal to grid voltages
frequency.
(2)Voltage ( Volt ) : The line voltages produced by the generator must be equal to the grid line voltages.
(3)Phase Sequence : The phase sequence of the voltages produced by the generator must be same at that of the grid.
(4)phase angle : The phase angle of voltages produced by the generator must be the same with that of grid voltages phase angle. (5) The waveform of the voltages produced by the generator must be the same with that of grid voltage.
| Is This Answer Correct ? | 8 Yes | 0 No |
It is better to have generator voltage slightly higher ( not exceeding 3 %) than grid voltage ,while synchronizing , to avoid leading pf on synchronization
| Is This Answer Correct ? | 3 Yes | 1 No |
Answer / abhilash
After satisfying x7 criteria......our required parameters (v,phase sequence,p angle,hz and etc )will achieve.......if any in this is not achieved we cannot approach with the grid........thank you
| Is This Answer Correct ? | 0 Yes | 0 No |
Difference between electrical and electronics?
why the steam turbine is not operated in home(base) load more than 1 hour kindly calrify
if suppose boiler has high heavy tube leakage, so in which time we feed the water in a boiler. can we stop the feed water at particular combustion temperature.
what is need of primary water system in power plant?
.What are the equipments should run when there is a black out in power plant.
What are the motors used in a thermal power plant? (With type and ht/lt) What voltage levels are used in a thermal power plant?
what is interview question for power plant
3 Answers Emerson, IOCL, SBPIL,
What is tripping relation between the turbine exhaust pressure and turbine last stage pressure....???
what does mean by kva rating
explain why direct on line starting toque and current may not be acceptable
can u please tell me how to calculate the concrete quantity for a under reamed pile? r=300mm,depth=3m for a cylinder and for bulb l=.750mm,width=.525
what is scanner air fan & how dose it work & is there any interlock in power plant
Civil Engineering (5086)
Mechanical Engineering (4456)
Electrical Engineering (16639)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)