what is the relation between the grid voltage and generator
voltage how to link up generator with grid
Answer Posted / muili ibrahim babatunde
This involves synchronization process. Hence, For the two voltages to link, these parameters must be met:
(1)Frequency ( Hz ) : The frequency of the voltages produced by the generator must be equal to grid voltages
frequency.
(2)Voltage ( Volt ) : The line voltages produced by the generator must be equal to the grid line voltages.
(3)Phase Sequence : The phase sequence of the voltages produced by the generator must be same at that of the grid.
(4)phase angle : The phase angle of voltages produced by the generator must be the same with that of grid voltages phase angle. (5) The waveform of the voltages produced by the generator must be the same with that of grid voltage.
| Is This Answer Correct ? | 8 Yes | 0 No |
Post New Answer View All Answers
im try to calculating seawater flow required for SW-FGD system. I need a guide, equation or method to do it, can some one help me! Thanks very much
What is surging in a centrifugal compressor ? How it occur's ? How is antisurging done ?
How do you consider that you can improve and what assistance do you need to achieve this
what is restricted earth fault explain in details
why is the in steam turbine axial displacement of active side thrust pad is positive and non active side thrust pad is negative.
what does mean by kva rating
operation
By any way can we increase the B check hours from 300 to 500
what's the moog valve
Why superheated are started before I'd and rd fan?
explain how the third harmonic content of the magnetising current affects transformer design
How to calculate power press toneage
Qatar Fertiliser Company (QAFCO) Shortlisted me for interview (got the intel from my source) for Field Operator- Utilities post. Please let me know what kind of questions they asked? ... this position requires 5 years of experience in Power Plant and background Diploma in Electrical/ Mech. ... my Background is Electrical and I am a sub Assistant Engineer (Operation) at a private HFO based Power plant... PS: Please Let me know what preparation should I take to obtain the Interview which will be take place In Bangladesh soon
our 125 kva DG does not start in AUTO mode works normally in MANUAL mode please give me a solution.....
how to differentiate between "ALL fuel lost" and "All Fuel Lost" in Boiler MFT condition?