For 1:2:4 ratio the weight of cement is 50 kgs then how many kgs are the
weight of sand and aggregate
Answers were Sorted based on User's Feedback
Answer / rajesh kumar
Cement= 50kg
so volumn= 50/1440 = 0.0347cum
Sand= 0.0347x2= 0.0694cum
Sand in kg= 0.0694x1600 = 111kg
Aggregate = 0.0347x4 = 0.139cum
Agg. in kg = 0.139x1700 = 236kg
| Is This Answer Correct ? | 8 Yes | 3 No |
Answer / uetian
weight of sand = 2/7 x 50 =14.28 kg
weight of aggregate = 4/7 x 50 = 28.57 kg
| Is This Answer Correct ? | 12 Yes | 11 No |
RATIO M15 1:2:4
CEMENT 1 Bag = 50 KG , Sand (River)=1840kg/cum,
Agg = 2850kg/cum
SAND =2/7
=0.285
=525 KG
AGG, = 4/7
=0.571
=1628kg
| Is This Answer Correct ? | 4 Yes | 5 No |
Please tell me about surveying standard chain details.Thanks.
8. What do you find more useful in your present work – your education or your practical experience from previous jobs or traineeships?
how material can be calculate for brick work in 1:6
Is there any alternate for plastering
How do you convert wind speed into force?
Please provide detail I.S standard code for using crush sand instead of river sand for plaster and concrete grade M15, M20, M25 and M30 and its mix design
1 Answers JPMorgan Chase, Sobha Developers, Structwel,
How many material do I need to finish a 340sqms using 190 block size and 700mm x 450mm x 200 mm concrete including of outside and inside plastering
apparatus of soundness test of cement
How much actual % of wastage of steel.
how to reduce size of column 450 x 750 to 230 x.... if it is cut in area of bathroom? means it appears in bathroon any shifting or any other option....building is g + 10 and the bathroom is at first floor...
As per Kandal suggestions, we have implemented rolling starts on 140 (+/- 5) degrees and we kept 3 rollars to complete the rolling before falling 125 degrees and the Aggregate AIV is below 22. But When the DBM bed is being rolled 3rd high viabration, (Before 1 plain & low ,2 high Viabrations), the aggregate is getting sharp edge agg. projections are damaged. As the literature is said that, the VG-30 Grade having better control the temp. susceptibility than Penetration grade. if so we could not get this problem at site. But we are facing on site. let me know.
why there is need to provide shear reinforcement?give the basic reason?
9 Answers JMC, L&T, Power Grid,
Civil Engineering (5086)
Mechanical Engineering (4453)
Electrical Engineering (16638)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)